Final Permitting Obtained

23 Jan 2015 10:55

RNS Number : 9943C
EMED Mining Public Limited
23 January 2015
 

AIM: EMED

TSX: EMD

 

EMED Mining Public Limited

("EMED" or the "Company")

 

 

Final Permitting Obtained

 

EMED Mining is pleased to announce that its wholly owned operating subsidiary EMED Tartessus ("EMEDT"), the holding company for the Rio Tinto Copper Project ("Proyecto Rio Tinto"), has received during a meeting with regional authorities at the Rio Tinto Mine the formal communication from the Mining authorities of the Government of Andalucía ("Junta de Andalucía") that the Resolution containing the granting of the Mining Permit for the Project has been signed. This global Mining Permit includes the approval of the Restoration Plan.

The granting of the Mining Permit and approval of the Restoration Plan are the last significant regulatory approvals required to be obtained by EMEDT before normal mining and processing operations can commence at Proyecto Rio Tinto during the third quarter of 2015.

 

During the first and second quarters of 2015 the Company will continue with construction and repair activities that have been ongoing at the Project since last summer. There are over 200 full-time employees together with numerous contractors working on site focussing mainly on plant and infrastructure refurbishment. The Company is targeting commissioning to commence during the third quarter of 2015.

 

In addition, selected mining and drilling contractors are working to optimise the production plan for the first five years of mining and preparing to start first mining activities during the second quarter of 2015.

 

Mining Permit and Restoration Plan Approval

 

The granting of the mining permit includes, as required by law, the approval of the Restoration Plan submitted by the Company. One of the conditions established by the Mining Permit is the placement by the Company to the Junta de Andalucía, within a stipulated period, of a Restoration Bond of 13.1 million. The Company is working with financial institutions to finalise arrangements for the bond.

 

The full content of the final Resolution containing the project approval will be sent to the company following the normal administrative procedure. It is expected that the Resolution will contain the project execution conditions to be fulfilled by the Company that are all in line with applicable Spanish laws.

 

The Company remains in close contact with its three key shareholders plus other key parties in order to finalise the funding of the Phase 1 development enabling the Company to achieve a 5Mtpa base case production as well as formally analysing the best options for a Phase 2 expansion that could take the planned production beyond the original 9 Mtpa feasibility case.

 

Alberto Lavandeira, CEO of the Company commented: "The approval of the Mining Permit is a major historic milestone for Proyecto Rio Tinto and paves the way for commissioning to commence in the third quarter of this year. On behalf of the Board of Directors I want to congratulate the team at Proyecto Rio Tinto who have undertaken a significant amount of work to achieve this key milestone. I would also like to thank the key shareholders for their constant and loyal support. The Company continues to work with its major stakeholders to finalise financing arrangements for the Phase 1 development of Proyecto Rio Tinto as well as analysing the best expansion options and I look forward to providing further updates in due course."

 

23 January 2015

Enquiries

 

EMED Mining

Roger Davey/Alberto Lavandeira

+34 959 59 28 50

Canaccord Genuity

Neil Elliot/Mark Palmer

+44 207 523 8000

Fox-Davies Capital

Oliver Stansfield

+44 203 463 5061

Walbrook PR

Nick Rome

+44 207 933 8783

For further information on the Company's activities, visit www.emed-mining.com.

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
MSCSEDFSDFISEIF
Date   Source Headline
22nd Dec 20107:00 amRNSEvaluation of Regua Tungsten Deposit Commences
20th Dec 20101:42 pmRNSCloses $32.5 million fundraising
15th Dec 20107:00 amRNSProgress at Proyecto Rio Tinto
14th Dec 20107:00 amRNSFiles Final Prospectus & Announces Terms of Offer
6th Dec 20107:00 amRNSIssue of Shares
22nd Nov 20109:30 amRNSResult Of EGM
22nd Nov 20107:00 amRNSUpdate Regarding EGM
5th Nov 20107:00 amRNSDespatch of EGM Circular
21st Oct 20107:00 amRNSFiles Preliminary Prospectus in Canada
21st Oct 20107:00 amRNSFiles Preliminary Prospectus in Canada
11th Oct 20109:00 amRNSAppointment of Joint AIM Broker
6th Oct 20107:00 amRNSQuarterly Report
20th Sep 20107:00 amRNSInterim Results
20th Aug 20107:00 amRNSIssue of Shares
18th Aug 20107:00 amRNSPRT Permitting Progress
30th Jul 20107:00 amRNSQuarterly Report
15th Jul 20107:00 amRNSExploration drilling commences in central Slovakia
5th Jul 20107:00 amRNSUpdate
28th Jun 20107:00 amRNSBiely Vrch update
15th Jun 201011:30 amRNSResult of AGM
8th Jun 20107:00 amRNSProyecto Rio Tinto Update
17th May 20107:00 amRNSProyecto Rio Tinto Update
12th May 20107:00 amRNSFinal Results
10th May 20109:00 amRNSIssue of Equity
4th May 20107:00 amRNSResult of EGM
23rd Apr 20107:00 amRNSBoard Appointment
22nd Apr 20107:00 amRNSElectricity connection to Proyecto De Rio Tinto
19th Apr 20107:00 amRNSQuarterly Report
15th Apr 20107:00 amRNSEMED Mining Raises ?8.775 Million in Placing
24th Mar 20102:18 pmRNSProyecto Rio Tinto Update
18th Mar 20109:09 amRNSProposed Dual-listing on the ASX
3rd Mar 20107:00 amRNSBiely Vrch and Slovakia gold exploration update
24th Feb 20102:30 pmRNSIssue of shares
16th Feb 20107:00 amRNSProyecto Rio Tinto Update
10th Feb 20107:00 amRNSProyecto Rio Tinto Update
2nd Feb 20107:00 amRNSProyecto Rio Tinto Update
1st Feb 20107:00 amRNSQuarterly Report
25th Jan 20109:12 amRNSResult of EGM
14th Jan 20107:00 amRNSUpdate of site activities at Proyecto Rio Tinto
6th Jan 20103:45 pmRNSEGM Circular
24th Dec 20099:07 amRNSIssue of Share Options
23rd Dec 20099:09 amRNSResult of EGM
17th Dec 20097:00 amRNSRefined permit roadmap for Rio Tinto mine start-up
4th Dec 20093:33 pmRNS?3.27 million placing
1st Dec 200912:11 pmRNSManaging Director's Presentation - Mines and Money
30th Nov 20097:00 amRNSProyecto Rio Tinto Update
27th Nov 200910:38 amRNSIssue of Shares
24th Nov 20097:00 amRNSRio Tinto Mine - permit processes move forward
26th Oct 20097:00 amRNSQuarterly Report
21st Oct 20097:00 amRNSUpdate on gold exploration in Slovakia

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.