We would love to hear your thoughts about our site and services, please take our survey here.

Less Ads, More Data, More Tools Register for FREE

Pin to quick picksAtalaya Mining Regulatory News (ATYM)

Share Price Information for Atalaya Mining (ATYM)

London Stock Exchange
Share Price is delayed by 15 minutes
Get Live Data
Share Price: 441.50
Bid: 438.50
Ask: 440.00
Change: 13.00 (3.03%)
Spread: 1.50 (0.342%)
Open: 435.00
High: 443.00
Low: 425.00
Prev. Close: 428.50
ATYM Live PriceLast checked at -

Watchlists are a member only feature

Login to your account

Alerts are a premium feature

Login to your account

2017 Operations Update and 2018 Guidance

22 Jan 2018 07:00

RNS Number : 4633C
Atalaya Mining PLC
22 January 2018
 

22 January 2018

Atalaya Mining Plc

("Atalaya" or the "Company")

2017 Operations Update and 2018 Guidance

 

Atalaya Mining plc (AIM:ATYM, TSX:AYM) is pleased to announce its operations update for the calendar year 2017 and to provide operational guidance for 2018.

 

PROYECTO RIOTINTO

 

Fourth quarter

Third quarter

Full year

2017

2016

2017

2017

2016

2018 Guidance

Ore mined

(M tonnes)

2.5

2.3

2.4

9.3

6.8

9.7

Waste mined

(M tonnes)

5.7

3.6

5.2

19.8

13.5

16.5

Ore milled

(M tonnes)

2.3

2.0

2.2

8.8

6.5

9.6

Cu grade

(%)

0.44

0.52

0.58

0.49

0.48

0.48

Cu recovery

(%)

86.11

84.77

85.95

85.45

82.99

84 - 86

Cu production

(tonnes)

8,622

8,938

10,679

37,164

26,179

37,000 - 40,000

 

Copper production at Proyecto Riotinto for 2017, the first full year of commercial production, was 37,164 tonnes up from 26,179 tonnes reported in 2016. For 2017 the operation reported a cumulative throughput rate of 8.8Mtpa with average copper head grade of 0.49% and a recovery rate of 85.45%. On a comparative basis to 2016, throughput has increased as operations were stabilised, copper grade was consistent with estimates and recovery has improved materially. Throughput rates and recoveries for Q4 were slightly better than in Q3 with copper head grade impacting metal contained in concentrate. Third quarter 2017 reported record quarterly copper production at Riotinto.

 

Guidance for copper production for 2018 is estimated to be in the range of 37,000 to 40,000 tonnes.

 

Mining operations are now running stable quarter-on-quarter. On a combined basis, ore, waste and marginal ore amounted to 3.1Mm3 in Q4 2017 versus 2.7Mm3 in Q3 2017. The new mining fleet, commissioned during the previous quarter, is now fully operational. Two additional production drill rigs and a 90,000-litre water bowser were delivered to site. At the processing plant, hourly throughput rate has improved compared with previous quarters owing to higher equipment availability.

 

As part of the Company´s continuous improvement programme, the installation of an additional secondary cone crusher is under evaluation. Liner installation at the tailings storage facilities was completed during the quarter. Improvements to process and water supply systems are under way.

 

Rehabilitation trials were initiated in the first bench of the south waste dump facility. Dust emission indicators remain below legal requirements. Installation of a dome covering the coarse ore stockpile to help with dust control is ongoing with civil foundations completed and structural fabrication under way. Dewatering of the Atalaya pit continues as previously reported.

 

On-site concentrate inventories at the end of the quarter were approximately 3,000 tonnes. All concentrate in stock at the beginning of the quarter and produced during the quarter was delivered to the port at Huelva.

 

Copper prices rose during the quarter with an average realised price per pound of copper payable, including the QPs closed in the period, of $2.87/lb compared with $2.18/lb in Q4 2016 and $2.66/lb in Q3 2017. The average spot copper price during the quarter was $3.09/lb. The realised price of shipments during the quarter excluding QPs was approximately $3.10/lb.

 

All-in sustaining costs ("AISC") for 2017 slightly increased mainly driven by the foreign exchange rate of USD and Euro. Further details on operating cost will be provided together with the Financial Statements but Management expects AISC to be in the range of $2.05/lb to $2.20/lb.

 

Near-mine exploration continued drilling the north-west extension of the Cerro Colorado pit. An infill drilling campaign in Cerro Colorado pit was initiated and is planned to last for most of 2018. An updated resources and reserves statement is being prepared as part of the expansion to the 15Mtpa Project. An airborne VTEM geophysical survey was completed during the quarter with results expected in Q1 2018.

 

The archaeological investigation currently under way in a section of the northern wall of Cerro Colorado pit has progressed down to the first of three levels. The programme is scheduled to last for all of 2018 with the area then released for mining after completion.

 

EXPANSION TO 15Mtpa AT PROYECTO RIOTINTO

 

The expansion project to 15Mtpa was formally approved during Q4 2017 and therefore launched at the beginning of December 2017. Process flowsheet, basic design criteria and preliminary layouts were established. Financing to initiate the expansion was raised through a placing of new shares and this allowed long lead equipment to be identified following a tender process and purchase orders were issued according to the schedule. The expansion is on track to deliver increased production by 2019.

 

PROYECTO TOURO

 

Permitting of Proyecto Touro continues to progress according to schedule. A number of reports were received as part of the permitting process where certain project improvements have been suggested. The Company has already engaged a number of consultants to address these recommendations.

 

The technical report is substantially completed at pre-feasibility level of detail and in compliance with NI 43-101 guidelines. The report will be released when the additional project improvements are incorporated to accommodate the final permitting process.

 

The exploration campaign initiated the previous quarter on newly optioned exploration concessions around Proyecto Touro is under way continuing. As part of the campaign a first phase of an airborne VTEM geophysical survey was completed with results expected in Q1 2018.

 

Alberto Lavandeira, CEO commented:

"Our first full year of production has been very satisfactory with continuously improving throughput and recoveries at historic highs and we are confident that our production guidance for 2018 will be on track. The decision to increase the plant's throughput to 15Mtpa marks another milestone in the regeneration of Proyecto Riotinto and we look forward to announcing revised reserves and resources in due course to meet this expansion. The VTEM geophysical surveys conducted at both Riotinto and Touro are complete and we expect the results to be forthcoming during the first quarter."

This announcement contains inside information for the purposes of Article 7 of Regulation (EU) no 596/2014.

 

Contacts:

Newgate Communications

Charles Chichester / James Ash / James Browne

+44 20 7680 6550

Canaccord Genuity (NOMAD and Joint Broker)

Henry Fitzgerald-O'Connor / Martin Davison / James Asensio

+44 20 7523 8000

BMO Capital Markets (Joint Broker)

Jeffrey Couch/Neil Haycock/Tom Rider

+44 20 7236 1010

 

This information is provided by RNS
The company news service from the London Stock Exchange
 
END
 
 
DRLPGUBCGUPRPGG
Date   Source Headline
24th Apr 202412:51 pmRNSPublication of Prospectus
11th Apr 20247:00 amRNSQ1 2024 Operations Update
19th Mar 20247:00 amRNS2023 Annual Results
8th Mar 20247:00 amRNSNotice of 2023 Annual Results
9th Feb 20247:00 amRNSIssue of Equity
18th Jan 20247:00 amRNSQ4 Operations Update and 2024 Production Guidance
21st Dec 20237:01 amRNSUpdate on Move to Main Market
21st Dec 20237:00 amRNSHolding(s) in Company
21st Dec 20237:00 amRNSHolding(s) in Company
20th Dec 20237:00 amRNSHolding(s) in Company
14th Dec 20231:49 pmRNSExtension of Port Handling Agreement
12th Dec 202311:28 amRNSResults of the 2023 Extraordinary General Meeting
12th Dec 20237:00 amRNS2023 Extraordinary General Meeting Statement
1st Dec 20237:00 amRNSHistorical Related Party Transactions
20th Nov 20237:00 amRNSHolding(s) in Company
16th Nov 20237:00 amRNSQ3 and YTD 2023 Financial Results
14th Nov 20237:00 amRNSProposed Re-domiciliation and Notice of EGM
13th Nov 20237:00 amRNSIntention to Move from AIM to Main Market
2nd Nov 20237:00 amRNSNotice of Q3 and YTD 2023 Financial Results
12th Oct 20237:00 amRNSQ3 2023 Operations Update
10th Oct 20233:11 pmRNSDirector/PDMR Shareholding
12th Sep 20237:00 amRNSInterim Dividend Foreign Exchange Rates
10th Aug 20237:00 amRNSQ2 and H1 2023 Financial Results
27th Jul 20237:00 amRNSNotice of Q2 and H1 2023 Financial Results
20th Jul 20237:00 amRNSFinal Dividend Foreign Exchange Rates & Payment
20th Jul 20237:00 amRNSCorrection to Q2 Provisional Revenue Adjustments
12th Jul 20237:00 amRNSQ2 2023 Operations Update
10th Jul 20237:00 amRNSPDMR Shareholding
29th Jun 20237:00 amRNS2022 Final Dividend Timetable
28th Jun 202311:25 amRNSResults of the 2023 Annual General Meeting
28th Jun 20237:00 amRNS2023 Annual General Meeting Statement
26th Jun 20237:00 amRNSReport on Payments to Governments
26th Jun 20237:00 amRNSApproval to Cease to be Reporting in Canada
1st Jun 20237:00 amRNSNotice of AGM
30th May 20237:00 amRNSApplication to Cease to be a Reporting Issuer
23rd May 20237:00 amRNSGrant of Share Options and PDMR Notification
16th May 20237:00 amRNSPublication of 2022 Sustainability Report
15th May 20237:00 amRNSQ1 2023 Financial Results
2nd May 20237:00 amRNSNotice of Q1 2023 Results
17th Apr 20237:00 amRNSQ1 2023 Operations Update
28th Mar 20237:00 amRNSEnvironmental Authorisation Granted to PMV
24th Mar 20237:00 amRNSFiling of New Riotinto PEA Technical Report
23rd Mar 20234:35 pmRNSPrice Monitoring Extension
22nd Mar 20237:00 amRNS2022 Annual Results
15th Mar 20237:00 amRNSNotice of 2022 Annual Results
13th Mar 20237:00 amRNSUpdate on Voluntary Delisting From The TSX
23rd Feb 20237:00 amRNSResults of New PEA for Riotinto
20th Feb 20237:00 amRNSVoluntary Delisting from the TSX
17th Jan 20237:00 amRNSQ4 Operations Update and 2023 Production Guidance
12th Jan 20237:00 amRNSHolding(s) in Company

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.

Login to your account

Don't have an account? Click here to register.

Quickpicks are a member only feature

Login to your account

Don't have an account? Click here to register.