Uis Tin Mine Operational Update

28 May 2019 07:00

RNS Number : 2244A
AfriTin Mining Ltd
28 May 2019
 

28 May 2019

AfriTin Mining Limited

("AfriTin" or the "Company")

Uis Tin Mine Operational Update

AfriTin Mining Limited (AIM: ATM), a mining company with a portfolio of near production tin assets in Namibia and South Africa, with the flagship asset being the Uis Tin Mine in Namibia ("Uis"), is pleased to provide an operational update relating to its mining and processing facility at Uis as part of the Phase 1 Pilot Plant project.

Highlights:

- Phased processing plant commissioning started;

- Mining contractor mobilised;

- Workforce recruitment nearing completion;

- Water and power infrastructure in place;

- Resource validation drilling completed with twenty holes drilled; and,

- Additional financing & working capital facility secured.

 

Commissioning of the processing plant at Uis has now commenced and is being conducted in a phased manner, starting with the testing of mechanical installations and progressing to continuous ore beneficiation. The plant consists of two main parts: a 4-stage crushing circuit and a 3-stage concentrating circuit. The C4 stage of commissioning, which involves passing ore material through the circuit, is scheduled for end of May 2019 for the crushing circuit and end of June 2019 for the concentrating circuit. During the commissioning, the plant will produce initial tin concentrate; however, hot commissioning and continuous plant operations will likely commence in July 2019. This represents a slight deviation from previous guidance by the Company stating that commercial tin concentrate production will commence in Q2 2019. The is due to longer than expected lead times in the procurement of equipment, material and construction services.

Commissioning will be followed by a production ramp up spanning four months with the goal of achieving design capacity before the end of Q4 2019.

Mining contractors have been mobilised and have commenced with continuous mining operations at the Uis mine. Initially, outcropping pegmatites of the V1 and V2 ore bodies will be targeted, utilising an opencast mining method and production will be ramped up according to the schedule of the processing plant. AfriTin is conducting overburden stripping at a ratio of 1.5 tonnes of overburden to one tonne of ore so as to ensure the sustainable exposure of ore over the life of the Phase 1 operation.

The Company is in the process of recruiting operational personnel. Approximately one third of the total planned complement of 90 people have been appointed, including the entire management team.

General infrastructure to the operation is now in place, including water supply from groundwater sources and electrical power supply from diesel generating sets. As per the announcement of 8 May 2019, the Company has concluded an agreement with the Namibian Power Corporation for provision of grid electrical power. Construction of the infrastructure required for the grid power connection has started.

The Company has completed exploration drilling (twenty holes) aimed at validating the historical mineral resource information by SRK in 1985, for ISCOR, for the V1 and V2 pegmatites. The first five holes have been announced (refer to announcement of 20 May 2019) and outstanding assay results are expected during June 2019.

The completion of the Phase 1 Pilot Plant project and ramp up to steady-state production are supported by an equity fund raising and a general working capital facility as announced by the Company on 22 May 2019.

At Uis, formerly the world's largest hard-rock tin mine, management are employing a two-fold strategy: the Phase 1 Pilot Plant is designed to process approximately 500,000 tonnes per annum producing approximately 60 tonnes of tin concentrate per month while Phase 2 will comprise a planned operation of a 3 million tonne per annum processing facility, producing approximately 5,000 tonnes per annum of tin concentrate.

Commenting on the developments CEO Anthony Viljoen stated, "We have been looking forward to this exciting phase of the project since breaking first ground at the end of 2018. While there is work to be done to achieve steady state production, the significant step of commencing production and first concentrate is a momentous milestone for the company. Bringing a project of this scale and stature into a supply constrained tin market, less than two years since our admission to AIM, I believe this places Afritin as a player of significance in the global tin market."

The information contained within this announcement is deemed by the Company to constitute inside information under the Market Abuse Regulation (EU) No. 596/2014.

 

For further information, please visit www.afritinmining.com or contact:

 

AfriTin Mining Limited

Anthony Viljoen, CEO

+27 (11) 268 6555

Nominated Adviser and Joint Broker

WH Ireland Limited

Katy Mitchell

James Sinclair-Ford

+44 (0) 207 220 1666 

Corporate Adviser and Joint Broker

H&P Advisory Limited

Andrew Chubb

Jay Ashfield

Nilesh Patel

+44 (0) 20 7907 8500

Joint Broker

NOVUM Securities Limited

Jon Belliss

+44 (0)20 7399 9400

Financial PR (United Kingdom)

Tavistock

+44 (0) 207 920 3150

Jos Simson

Barney Hayward

 

About AfriTin Mining Limited

Notes to Editors

AfriTin Mining is the first pure tin company listed in London and its vision is to create a portfolio of world-class, conflict-free, tin producing assets. The Company's flagship asset is the Uis brownfield tin mine in Namibia, formerly the world's largest hard-rock tin mine.

AfriTin is managed by an experienced board of directors and management team with a current two-fold strategy: fast track Uis brownfield tin mine in Namibia to commercial production in 2019 ramping up to 5,000 tonnes of concentrate, and consolidation of other quality African tin assets. The Company strives to capitalise on the solid supply/demand fundamentals of tin by developing a critical mass of tin resource inventory, achieving production in the near term and further scaling production by consolidating tin assets in Africa.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDEAFSXAEENEAF
Date   Source Headline
27th May 20267:00 amRNSUis Financing & Lithium Ridge Drilling Complete
8th May 20269:45 amRNSNotification of Major Holdings
5th May 20267:00 amRNSSecond Batch of Lithium Ridge Drill Results
29th Apr 20268:31 amRNSNotification of Major Holdings
29th Apr 20267:00 amRNSAmendment of Convertible Loan Notes
24th Apr 20262:09 pmRNSNotification of Major Holdings
23rd Apr 20267:08 amRNS-RUpdate: Investor Presentation via IMC
20th Apr 20267:00 amRNSStrategic Equity Placement To Accelerate Growth
13th Apr 20267:00 amRNSPositive Tungsten Test Results At Brandberg West
26th Mar 20267:00 amRNSBusiness Update For Period Ended 28 February 2026
3rd Mar 20264:03 pmRNSEmployee Incentive Scheme Update
24th Feb 20267:00 amRNSThaisarco Strengthens Relationship with Andrada
10th Feb 20262:40 pmRNSEIB Partnership for Uis Mine Feasibility Study
9th Feb 20267:00 amRNSHigh-grade initial drill results at Lithium Ridge
4th Feb 20267:00 amRNSACAM Transaction Update
26th Jan 20267:00 amRNSLithium Ridge Exploration Update
21st Jan 20267:00 amRNSPartnership with ACAM to develop Brandberg West
19th Jan 202611:00 amRNSOrange Trust Loan Conversion to Equity
17th Dec 20257:00 amRNSQ3 Operational Update For Period End 30 Nov 2025
1st Dec 202510:35 amRNSNotification of Major Holdings
27th Nov 20257:00 amRNSInterim Results for Six Months Ended 31 Aug 2025
7th Nov 20257:00 amRNS-RPublication of 2025 Sustainability Report
24th Oct 20255:26 pmRNSNotification of Major Holdings
24th Oct 20255:25 pmRNSNotification of Major Holdings
30th Sep 20252:00 pmRNSResults of the Annual General Meeting
29th Sep 20257:00 amRNSBoard Changes
15th Sep 20257:00 amRNSQ2 Operational Update For Period Ended 31 Aug 2025
3rd Sep 20257:00 amRNSExploration Drilling Commences at Lithium Ridge
29th Aug 20257:00 amRNSAudited Financial Results For Year End 28 Feb 2025
21st Aug 20257:00 amRNSAndrada accelerates growth of its tin production
15th Aug 20257:00 amRNSIssuance of Shares & Total Voting Rights
27th Jun 20257:00 amRNSResults of strategic Subscription & Placing
26th Jun 20257:00 amRNSProposed Strategic Subscription and Placing
19th Jun 20252:00 pmRNSNotification of Major Holdings
17th Jun 20257:00 amRNSAndrada Secures High-Grade Tin Feedstock
6th Jun 20257:00 amRNSOperational Update For Period Ended 31 May 2025
22nd May 202511:28 amRNSChange of Registered Address
10th Apr 20257:00 amRNSUis Exploration Drilling Results
31st Mar 20257:00 amRNSFY Operational Update For Period Ended 28 Feb 2025
11th Mar 202512:59 pmRNSNotification of Major Holdings
7th Mar 202512:41 pmRNSNotification of Major Holdings
4th Mar 20254:51 pmRNSDirector/PDMR Shareholding
28th Feb 20257:00 amRNSSQM earn-in agreement receives NaCC Approval
21st Feb 20252:17 pmRNSEmployee Incentive Scheme Update & Issue of Shares
14th Feb 202512:20 pmRNSNotification of Major Holdings
12th Feb 20257:00 amRNSOrange Trust Funding
6th Feb 20257:00 amRNSMineral Resource Update at Uis
20th Dec 20247:00 amRNSQ3 Operational Update for Period Ended 30 Nov 24
28th Nov 20247:00 amRNSUnaudited Interim Results 6 Months Ended 31/08/24
20th Nov 20247:00 amRNSPublication of 2024 Sustainability Report

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.