Public infrastructure upgrades improve BKM project

19 Sep 2019 07:00

RNS Number : 9246M
Asiamet Resources Limited
19 September 2019
 

 

19 September 2019

 

Public infrastructure upgrades improve BKM project transport and logistics

 

Asiamet ("ARS" or the "Company") is pleased to announce that a number of recent government infrastructure initiatives and planned upgrades to bridges and roads within Central Kalimantan is expected to significantly improve transport and logistics options for the BKM Copper project and result in reduced operating costs relating to the transport of supplies in and copper cathode out of the proposed BKM mine site.

Post completion of the BKM feasibility study, the Company is currently reviewing a number of options and alternatives to add significant further value to the BKM copper project, (as announced on 14 June 2019). The assessment of planned public infrastructure works was undertaken as part of these value enhancement studies.

A review of the logistics and transport section of the study yielded some potential high value alternatives, one being the use of the Bagendang Port (Sampit Port) compared with the Banjarmasin Port used in the BKM Feasibility Study. Recent infrastructure initiatives and planned upgrades to government bridges and roads have now allowed the study team to review this alternative route as a preferred logistical hub.

This revised option would result in:

·; a more efficient turnaround time for the transport of supplies and copper cathode in and out of site.

·; a saving of approximately 140 kilometres per one way trip or 280 kilometres per round trip. The distance from the BKM site to Banjarmasin Port is approximately 495 kilometres compared with approximately 350 kilometres from site to the Sampit Port. A map comparing the two logistical routes is shown in Figure 1.

·; improvement in project operating costs by several millions of dollars over the initial life of mine due to the shorter logistics distance. As the detailed costings are finalised the outcomes will be reported.

The Sampit Port as shown in Figure 2, is an established container terminal for smaller vessels and cargo and would suit the operations of the BKM project. Included in recent upgrades is a major new bridge being constructed at Samba as per Figure 3 below.

 

Peter Bird, Asiamet's CEO commented:

"Following completion of the BKM Feasibility Study the Asiamet team has continued to focus on further enhancing the value of the BKM Copper project through the assessment of a number of opportunities identified and reported on as part of the study. The refinement of the logistics route to Sampit Port and the associated reduction in operating costs over the life of mine is an excellent example of the value expected to be delivered from this process. Our team along with our technical service providers are systematically working through the 15 identified opportunities and expect to report further positive results as they come to hand.

The BKM Copper project remains one of the most advanced copper projects in Asia at a time when global mine supply is forecast to move into deficit. The delivery of a robust Feasibility Study and the opportunity for further significant upside through value engineering and exploration has increased awareness of the BKM project amongst a number of strategic investors and potential partners with whom discussions are continuing."

 

Figure 1 Insert Map of site to Banjarmasin Port and Bagendang Port. To view the image, click on the link below http://asiametresources.com/assets/img/ars_1_180919.png 

Figure 2 Bagendang Port in Sampit. To view the image, click on the link below http://asiametresources.com/assets/img/ars_2_180919.png

Figure 3 Bridge Construction at Samba. To view the image, click on the link below http://asiametresources.com/assets/img/ars_3_180919.png

 

Value Enhancement Program - Background details

The Value Enhancement (VE) program was reported in the Feasibility Study for the BKM project (announced 14 June 2019). This process identified and ranked 20 opportunities ranging in value delivery and ease of implementation. These VE opportunities were risk adjusted and totalled an estimated $35M (excludes exploration success) in additional value that can be added to the BKM project value. Larger impact initiatives include:

·; pre-treatment of the currently discarded, less-leachable heap leach ore types such as chalcopyrite by utilising the Albion Leaching technology (~$20M);

·; improved mineralisation geological controls by incorporating detailed structural geology model (~$5M);

·; an electricity supply scope change from gas supply to local coal supply (~$4M);

·; further refining the methodology of ore block classification to enhance metal and commercial returns (~$3.5M);

·; reducing construction earthworks costs by sourcing locally and delivering synergies by working with the mining contractor (~$3M); and

Over and above these VE initiatives, review of near mine exploration for targets proximal (less than 3km) to the BKM Resource that have the potential to add significant value was also considered. These targets may add treatable copper resources to that already defined or create further opportunities for revenue enhancement through direct shipping of ore. The high priority targets to be investigated immediately include:

·; BKM 'link zone target' the immediate zone between BKM and BKZ;

·; Testing of IP chargeability highs approximately 800m to the north-west if BKM;

·; BKM depth extensions through deeper drilling to follow up IP chargeability at depth; and

·; BK-South near surface oxide targets, maybe amenable to SX-EW process and augment the current mine life at BKM.

The Company has completed and lodged all required documentation in relation to the permits required for exploration access of the abovementioned targets and mobilisation of drilling equipment is anticipated in early-mid Q4 2019.

 

 

ON BEHALF OF THE BOARD OF DIRECTORS

Peter Bird, Deputy Chairman and CEO

For further information, please contact:-Ends-

 

Peter BirdDeputy Chairman and CEO, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: peter.bird@asiametresources.com

 

Tony ManiniExecutive Chairman, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: tony.manini@asiametresources.com

 

FlowComms Limited

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: Sasha@flowcomms.com 

Asiamet Resources Nominated AdviserRFC Ambrian Limited

Andrew Thomson / Stephen Allen

Telephone: +61 8 9480 2500

Email: Andrew.Thomson@rfcambrian.com / Stephen.Allen@rfcambrian.com 

 

Berenberg

Matthew Armitt, Detlir Elezi

Telephone: +44 20 3207 7800

Email: Matthew.Armitt@berenberg.com / Detlir.Elezi@berenberg.com 

 

LiberumClayton Bush, Kane Collings

Telephone: +44 7773 322679

Email: Clayton.Bush@liberum.com 

 

Optiva Securities LimitedChristian Dennis

Telephone: +44 20 3137 1903

Email: Christian.Dennis@optivasecurities.com

 

Follow us on twitter @AsiametTweets

This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterised by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices. There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDEKLBFKKFLBBB
Date   Source Headline
26th May 20265:30 pmRNS2025 Annual Report & Financial Statements
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
29th Jan 20261:30 pmRNSResults of General Meeting
27th Jan 20265:30 pmRNSUpdate on Proposed Sale of Indokal (KSK Project)
17th Dec 20256:08 pmRNSUS$3.1 million Subscription
9th Dec 20251:55 pmRNSResults of Annual General Meeting
27th Nov 202512:45 pmRNSPDMR Dealing
14th Nov 202510:00 amRNSPDMR Dealing
12th Nov 20259:30 amRNSPDMR Dealing
10th Nov 20257:00 amRNSNotice of Annual General Meeting
6th Nov 202510:13 amRNSSale of Asiamet’s Interest in the KSK Project
6th Oct 202510:00 amRNSLong Term Incentive Programme
17th Sep 20257:00 amRNSDirector’s Fees and Employee Share-Based Payments
15th Sep 20257:00 amRNSBKM Copper Project Limestone Drilling Update
29th Aug 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
15th Aug 20257:00 amRNSLimestone Resource Drilling at BKM Copper Project
11th Aug 20257:00 amRNSAppointment of Project Director for BKM
18th Jul 20257:00 amRNSAppointment of Grant Samuel
15th Jul 20254:00 pmRNSCompletion of Subscription
9th Jul 20257:00 amRNSAppointment of Shore Capital as Corporate Broker
9th Jun 20255:15 pmRNSTR-1: Notification of major holdings
5th Jun 20257:00 amRNSCommencement of BKM Project Financing Process
29th May 20257:21 amRNSUS$2.5 million Subscription
29th May 20257:07 amRNS2024 Annual Report & Financial Statements
20th May 20257:00 amRNS-RBKM Stage 1 OFS – Investor Presentation and Q&A
15th May 20257:00 amRNSCompletion of BKM Feasibility Study ITE Report
7th May 20257:00 amRNSBKM Copper Project Optimised Feasibility Study
2nd May 202512:15 pmRNSUpdated Ore Reserve for BKM Stage 1
24th Apr 20257:00 amRNSPower Study Completes Inputs for Feasibility Study
28th Mar 20257:00 amRNSBKM Optimised Feasibility Study Near Completion
23rd Dec 20243:00 pmRNSBKM Capital Cost Estimate Reduced by US$58 Million
17th Dec 202410:00 amRNSDirector’s Fees and Employee Incentive Payments
26th Nov 202411:30 amRNSAppointment of Head of Corporate Finance
14th Nov 20247:00 amRNSBKM Copper Project Optimisation Works Update
18th Oct 20245:00 pmRNSSuccessful Completion of US$3.55 million Raise
15th Oct 20242:30 pmRNSRetail Offer
15th Oct 20242:25 pmRNSUS$3.3 million Subscription
7th Oct 20247:05 amRNSBoard Changes
30th Sep 202412:00 pmRNSInterim Results for Six Months Ended 30 June 2024
22nd Aug 202411:30 amRNSMaterial Capex Reductions for BKM Copper Project
26th Jun 20244:30 pmRNSResult of AGM
25th Jun 20247:00 amRNSBKM Copper Project Optimisation
3rd Jun 202410:00 amRNSNotice of Annual General Meeting
14th May 20247:00 amRNSBKM Heap Leach Facility Earthworks Optimisation
9th May 202411:45 amRNS2023 Annual Report & Financial Statements
17th Apr 20247:00 amRNSBKM High Grade Copper Rock Sample Results
28th Mar 20247:00 amRNSBKM Project Engineering Design & Execution Update
27th Mar 20247:00 amRNSSustainable Power Solution for BKM Copper Project
1st Mar 20247:04 amRNSCorporate Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.