BKM Copper Project Optimisation

25 Jun 2024 07:00

RNS Number : 7463T
Asiamet Resources Limited
25 June 2024
 

25 June 2024 

 

 

BKM Copper Project Optimisation

BKM Stage 1 Project Physicals to Considerably Reduce Upfront Capital

 

Asiamet Resources Limited ("Asiamet" or the "Company") is pleased to provide a further update on optimisation work for the BKM heap leach project in Central Kalimantan, Indonesia ("BKM" or the "BKM Copper Project").

Following the recent announcement of the BKM heap leach facility ("HLF") earthworks optimisation results, the Company has made further significant advancements to lower the initial capital expenditures required to reach first production.

As previously announced, a revised HLF location allows for a staged construction of the HLF pad, significantly reducing bulk earthworks and upfront capital costs. This strategic change is expected to shorten construction timelines, move HLF construction off the critical path in the project development schedule and expedite timelines to first revenue and cashflow.

Following on from this HLF optimisation work, the Company has focused its efforts on additional opportunities identified to further reduce pre-production capital expenditure and execution risk in the initial phase of the BKM mine development. The first stage of the BKM Copper Project will focus on developing a smaller capacity, higher-grade, higher-margin mine centred around a revised open pit design which sits entirely within the footprint of the 2023 BKM Feasibility Study (FS) pit. The new pit design is expected to considerably lower the upfront capital cost, improve operating efficiencies and lower construction risk.

The major benefits emanating from these optimisation works are expected to flow through to significantly enhanced project economics for BKM, as the Company continues to advance financing for the initial BKM mine development. The highlights below detail the key changes to the 2023 FS, based on the Company's internal work.

Highlights

Mining Physicals:

· 47% Decrease in Total Material Mined. LOM Strip Ratio Reduced from 1.37 to 0.72: New pit design moves 28Mt material compared to 38.4Mt. These large reductions in material movement reduce the total mining costs and accelerate project timelines. As the volume of waste material moved per tonne of ore extracted reduces, the life of mine ("LOM") strip ratio improves significantly from 1.37 to 0.72, improving mining efficiency, reducing operating costs, and enhancing project economics.

 

· Flexibility for Future Expansion: Crucially, the new pit design sits entirely within the 2023 FS pit design and allows for seamless future expansion of the mine to lift copper production capacity.

Processing Physicals:

 

· Higher Soluble Copper Grade: Ore processed is 28Mt at 0.55% soluble copper grade compared to 38.4Mt at 0.51% in the 2023 FS. Heap leach pad lift heights are reduced from 10m to 6.6m, allowing for earlier copper extraction and potentially accelerating first production of cathode. Although total cathode production direct from the heap leach reduces from 154.1kt over 10 years to 122.4kt over 13 years, the higher processed soluble copper grades and reduced heap leach pad lift heights are expected have the potential to enhance early-stage project cash flow and economics.

 

Heap Leach Facility Design:

· Staged Construction for Cost Efficiency: The new design of the BKM HLF allows for the first three years of stacking operations to be conducted on a much smaller area, reducing upfront construction requirements. In year three, the HLF pad will be extended to accommodate remaining stacking needs. The current total height of the HLF is 66.3m, which could be extended to approximately 72m to accommodate a total capacity of 29.2 million tonnes of ore stacked. This phased approach lowers initial capital expenditure, aligns construction with an expedited production timeline, and ensures cost-effective scalability.

The Company's engagement with Rexline Engineering and BGRIMM is advancing engineering design on the basis of the optimised BKM Copper Project plan, following completion of which updated cost estimates will be delivered. Further announcements will be made in due course.

Darryn McClelland, Chief Executive Officer, commented:

"The decision to optimise the development of the BKM Copper Project in stage 1 is a prudent approach which builds upon beneficial opportunities identified for an innovative redesign of the projects open pit and heap leach processing facility. This approach maximises operating efficiency and minimises upfront capital expenditures, while maintaining full flexibility for future expansions. By reducing pre-production capital costs and project footprint through the development of a smaller first stage heap leach facility, we are not only accelerating our path to production but also enhancing project economics and environmental sustainability. A more capital efficient, lower risk approach to the development of BKM sets a strong foundation for completing project financing and developing our first copper mine. 

Updated cost estimates for the project will flow through from the detailed design and engineering currently underway with Rexline Engineering and BGRIMM and the Company looks forward to providing regular updates to shareholders from ongoing works as they become available. These project optimisation outcomes together with work underway to lock down a fully baked power solution feed into the bank financing process."

BKM Copper Project Stage 1 Optimisation 

The fundamental change of position and design for the heap leach facility has led to an optimised approach to developing the BKM mine with a clear focus on reducing pre-production capex. Earthworks represent a major component of the upfront capital cost for the project and the new position, which sits within the current footprint of the BKM site, enables staging of the earthworks for developing the heap leach pad which was not possible in the previous position. Taking this into account, the approach to mining, processing and copper production was able to be compressed into a smaller footprint, smaller capacity and higher-grade stage 1 project which is expected to deliver a significantly lower pre-production capex cost and subsequently reduces the risk profile of the project. Project economics are expected to be significantly enhanced as a result of the physical design changes.

Table 1: Comparison of Key Production Physicals

Project Physical

 

2024 BKM Stage 1

2023 FS Update

Ore Mined

Mt

28.0

38.4

Waste Mined

Mt

20.0

52.5

Total Material Mined

Mt

48.0

90.9

Strip Ratio

#

0.72

1.37

Maximum Mining Rate

Mt/yr

5.5

15.5

Maximum Ore Treatment Rate

Mt/yr

2.6

4.5

Heap Leach Facility Lift Height

m

6.6

10

Soluble Copper grade

% Cu

0.55

0.51

Copper Production Period

Years

12.8

10

LOM Cathode Produced

kt

122.4

154.1

Avg Cathode Production

(Less First and Final Years)

ktpa

10.1

(11 years)

17.0

(8 years)

 

Key points emanating from optimisation works compared to the 2023 FS are:

· An incremental 10.4Mt of ore is available to mine at a strip ratio of 3.1. The updated approach does not preclude the Company from completing an expansion of the BKM pit to any feasible size dependent on future approach to economic ore extraction.

· The reduction in material movement leads to a large reduction in annual mining volumes. A flow on reduction in the overall capital and operating expenditure is expected from a reduction in the size and scale of the mining fleet required for the revised project bulk earthworks.

· The stage 1 mine plan considers only copper ore which can be recovered via low-cost heap leach processing. The Company continues to evaluate the best approach to maximizing copper extraction and creating value from the larger BKM JORC compliant resource base which sits outside the stage 1 mine plan.

· The significantly reduced footprint offers greater flexibility for the future allowing for a phased approach to development. Future expansions will be based on the ability to treat the primary sulphide copper resources at BKM and the integration of the BKZ polymetallic deposit.

· All process equipment is being scaled down to reflect the change in capacity and production requirements. The maximum copper production rate as defined by the Electrowinning Circuit design parameters is circa 11,000tpa.

 

ON BEHALF OF THE BOARD OF DIRECTORS

Darryn McClelland, Chief Executive Officer

-Ends-

 

For further information, please contact:

 

Darryn McClelland Chief Executive Officer, Asiamet Resources LimitedEmail: darryn.mcclelland@asiametresources.com

 

Tony Manini Executive Chairman, Asiamet Resources LimitedEmail: tony.manini@asiametresources.com

 

Investor Enquiries

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: Sasha@flowcomms.com / info@asiametresources.com

Nominated & Financial Adviser Strand Hanson Limited

James Spinney / James Dance / Rob Patrick

Telephone: +44 20 7409 3494

Email: asiamet@strandhanson.co.uk

  

Broker

Optiva Securities Limited Christian Dennis

Telephone: +44 20 3137 1903

Email: Christian.Dennis@optivasecurities.com

 

Follow us on twitter @AsiametTweets

 

FORWARD-LOOKING STATEMENT

This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterised by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices. There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDUVVVRSRUNURR
Date   Source Headline
26th May 20265:30 pmRNS2025 Annual Report & Financial Statements
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
29th Jan 20261:30 pmRNSResults of General Meeting
27th Jan 20265:30 pmRNSUpdate on Proposed Sale of Indokal (KSK Project)
17th Dec 20256:08 pmRNSUS$3.1 million Subscription
9th Dec 20251:55 pmRNSResults of Annual General Meeting
27th Nov 202512:45 pmRNSPDMR Dealing
14th Nov 202510:00 amRNSPDMR Dealing
12th Nov 20259:30 amRNSPDMR Dealing
10th Nov 20257:00 amRNSNotice of Annual General Meeting
6th Nov 202510:13 amRNSSale of Asiamet’s Interest in the KSK Project
6th Oct 202510:00 amRNSLong Term Incentive Programme
17th Sep 20257:00 amRNSDirector’s Fees and Employee Share-Based Payments
15th Sep 20257:00 amRNSBKM Copper Project Limestone Drilling Update
29th Aug 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
15th Aug 20257:00 amRNSLimestone Resource Drilling at BKM Copper Project
11th Aug 20257:00 amRNSAppointment of Project Director for BKM
18th Jul 20257:00 amRNSAppointment of Grant Samuel
15th Jul 20254:00 pmRNSCompletion of Subscription
9th Jul 20257:00 amRNSAppointment of Shore Capital as Corporate Broker
9th Jun 20255:15 pmRNSTR-1: Notification of major holdings
5th Jun 20257:00 amRNSCommencement of BKM Project Financing Process
29th May 20257:21 amRNSUS$2.5 million Subscription
29th May 20257:07 amRNS2024 Annual Report & Financial Statements
20th May 20257:00 amRNS-RBKM Stage 1 OFS – Investor Presentation and Q&A
15th May 20257:00 amRNSCompletion of BKM Feasibility Study ITE Report
7th May 20257:00 amRNSBKM Copper Project Optimised Feasibility Study
2nd May 202512:15 pmRNSUpdated Ore Reserve for BKM Stage 1
24th Apr 20257:00 amRNSPower Study Completes Inputs for Feasibility Study
28th Mar 20257:00 amRNSBKM Optimised Feasibility Study Near Completion
23rd Dec 20243:00 pmRNSBKM Capital Cost Estimate Reduced by US$58 Million
17th Dec 202410:00 amRNSDirector’s Fees and Employee Incentive Payments
26th Nov 202411:30 amRNSAppointment of Head of Corporate Finance
14th Nov 20247:00 amRNSBKM Copper Project Optimisation Works Update
18th Oct 20245:00 pmRNSSuccessful Completion of US$3.55 million Raise
15th Oct 20242:30 pmRNSRetail Offer
15th Oct 20242:25 pmRNSUS$3.3 million Subscription
7th Oct 20247:05 amRNSBoard Changes
30th Sep 202412:00 pmRNSInterim Results for Six Months Ended 30 June 2024
22nd Aug 202411:30 amRNSMaterial Capex Reductions for BKM Copper Project
26th Jun 20244:30 pmRNSResult of AGM
25th Jun 20247:00 amRNSBKM Copper Project Optimisation
3rd Jun 202410:00 amRNSNotice of Annual General Meeting
14th May 20247:00 amRNSBKM Heap Leach Facility Earthworks Optimisation
9th May 202411:45 amRNS2023 Annual Report & Financial Statements
17th Apr 20247:00 amRNSBKM High Grade Copper Rock Sample Results
28th Mar 20247:00 amRNSBKM Project Engineering Design & Execution Update
27th Mar 20247:00 amRNSSustainable Power Solution for BKM Copper Project
1st Mar 20247:04 amRNSCorporate Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.