Sustainable Power Solution for BKM Copper Project

27 Mar 2024 07:00

RNS Number : 4224I
Asiamet Resources Limited
27 March 2024
 

27 March 2024

 

Sustainable Power Solution for Remote Mining: KSK Biomass Feedstock Study Highlights

 

Asiamet Resources Limited ("Asiamet" or the "Company") is pleased to announce the successful completion of the KSK Biomass Feedstock Study, a crucial milestone in progressing a power solution for the Company's BKM copper cathode project in Central Kalimantan, Indonesia ("BKM" or the "BKM Copper Project"). Undertaken in collaboration with Britmindo Mining Services Singapore Pte Ltd, the study is a comprehensive assessment aimed at establishing a sustainable power solution for the BKM Copper Project within and/or proximal to Asiamet's KSK licence area, in which BKM is located.

The study, emphasising Asiamet's commitment to a renewable energy solution for the proposed greenfield BKM Copper Mine, addressed key parameters crucial for the development of a biomass power station in a remote mining region. All aspects referenced below will be developed in further detail once project execution and project development partners for the biomass power station are locked in, which are expected to be achieved in Q2 2024.

Highlights

· Abundant Biomass Feedstock Resources: Through an extensive in-field investigation, data collection and analysis, the study has identified ample biomass feedstock sourced primarily from palm oil mills within a 100km radius of the proposed power plant location that could feed a biomass power station dedicated to the BKM Copper Project. Robust feedstock supply not only ensures operational sustainability but also aligns with Asiamet's commitment to a renewable energy solution for BKM.

 

· Remote Mining Power Solution: The biomass power station offers a reliable, renewable energy solution for producing copper cathode at BKM. By leveraging local biomass resources, the project contributes to increased economic empowerment in the direct project area.

 

· Power Plant Location Assessment: Comprehensive evaluation concluded, proposing a unique cost-effective and lower carbon footprint transportation solution optimising available biomass transportation routes and significantly reducing the distance of the High-Voltage transmission line.

 

· Partnership model: Following the framework outlined in the 2023 Feasibility Study, the biomass power plant will be operated by a third party who will be responsible for its construction, operation and maintenance. Asiamet is actively engaged in advanced discussions with potential partners interested in fully financing the dedicated biomass power plant for the BKM Copper Project and will make a further announcement relating to an MOU or similar agreement once this is complete.

 

· Sustainability Focus: The study underscores Asiamet's commitment to sustainable development by prioritising the use of renewable energy solutions to power BKM. Biomass feedstock sourcing from palm oil mills promotes circular economy principles and reduces reliance on fossil fuels.

  

Biomass Feedstock Study Scope of Work

The scope of work for the KSK Biomass Feedstock Study encompassed several key components aimed at establishing a sustainable power solution for the BKM Copper Project; these were as follows:

Identification of Palm Oil Mills

Initial efforts focused on identifying and evaluating biomass feedstock sources, with a particular emphasis on palm oil mills located within a 100km radius of the proposed power plant location. Rigorous field investigations and data analysis were conducted to assess the suitability and availability of biomass feedstock, ensuring a robust supply chain for the biomass power station. The palm oil derived biomass material is of value for its energy content however it remains a stranded asset due to its location. This opens the opportunity for use in power generation for the BKM Copper Project at relatively low cost.

Optimal Power Plant Location

Simultaneously, the study optimised biomass transportation routes by evaluating existing infrastructure and potential transport networks. This entailed detailed assessments to minimise transportation distances and associated costs while maximising logistical efficiency.

Site evaluations were then undertaken to identify suitable locations for the biomass power station, considering factors such as accessibility, environmental impact, and proximity to biomass feedstock sources.

Cost Analysis of Feedstock Transportation

Thorough analysis of transportation costs considers distance, terrain challenges, and environmental sustainability. Strategies to minimise carbon footprint and optimise logistical efficiency are integrated into transportation planning models.

Viability of Transmission Line Construction

Detailed assessments of transmission line route feasibility addressed terrain complexities and potential cost implications. Emphasis was placed on minimising environmental impacts and optimising energy transmission efficiency. Moreover, the feasibility of constructing high-voltage transmission lines to connect the biomass power station to the BKM Copper Project site was thoroughly assessed. This involved conducting detailed surveys to identify potential routes, evaluate terrain challenges, and assess environmental impact and regulatory requirements.

Integration of Sustainability Principles

Throughout the study, sustainability principles were paramount, with a focus on the use of renewable biomass feedstock and minimising environmental disruption aligning with Asiamet's commitment to responsible resource development and environmental stewardship.

 

Darryn McClelland, Chief Executive Officer, commented:

"In addition to our other ongoing workstreams and corporate development activity, the KSK Power Study exemplifies Asiamet's commitment to sustainable mining practices and renewable energy initiatives. By prioritising environmental stewardship and community engagement, Asiamet aims to set a benchmark for responsible resource development in remote mining regions.

"Securing a consistent, sustainable power supply is paramount for any mining project, and the proposed Biomass Power Station enhances the environmental sustainability of the BKM Copper Project. We are particularly encouraged by substantial interest from potential partners in financing the power plant. Further details will be shared in due course.

"Considering the recent material uplift in the copper price, our projects are being increasingly recognised for their strategic importance. According to analyst reports copper supply will be constrained for years to come necessitating the fast-tracking or acquisition of new projects to meet global demand; the lack of exploration in copper and new discoveries will mean copper prices will likely be at new higher levels for a prolonged period. With a defined power solution now coupled with its high-quality resources, Asiamet has a clear pathway to production at BKM and is well-positioned to capitalise on these trends. The Board and management remain highly committed to delivering value from our asset base for all stakeholders.

"We also look forward to providing a further update this quarter, specifically regarding the appointment of partners for the BKM front end engineering design ("FEED") and project execution. We believe that early engagement of our project execution partners will be key to BKM's success and underscores our focus on efficient and effective advancement of the BKM copper mine development."

 

ON BEHALF OF THE BOARD OF DIRECTORS

Darryn McClelland, Chief Executive Officer

-Ends-

 

For further information, please contact:

 

Darryn McClelland Chief Executive Officer, Asiamet Resources LimitedEmail: darryn.mcclelland@asiametresources.com

 

Tony Manini Executive Chairman, Asiamet Resources LimitedEmail: tony.manini@asiametresources.com

 

Investor Enquiries

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: Sasha.sethi@flowcomms.com / info@asiametresources.com

Nominated & Financial Adviser Strand Hanson Limited

James Spinney / James Dance / Rob Patrick

Telephone: +44 20 7409 3494

Email: asiamet@strandhanson.co.uk

  

Broker

Optiva Securities Limited Christian Dennis

Telephone: +44 20 3137 1903

Email: Christian.Dennis@optivasecurities.com

 

Follow us on twitter @AsiametTweets

 

FORWARD-LOOKING STATEMENT

This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterised by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices. There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
UPDEAADKAFXLEAA
Date   Source Headline
26th May 20265:30 pmRNS2025 Annual Report & Financial Statements
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
29th Jan 20261:30 pmRNSResults of General Meeting
27th Jan 20265:30 pmRNSUpdate on Proposed Sale of Indokal (KSK Project)
17th Dec 20256:08 pmRNSUS$3.1 million Subscription
9th Dec 20251:55 pmRNSResults of Annual General Meeting
27th Nov 202512:45 pmRNSPDMR Dealing
14th Nov 202510:00 amRNSPDMR Dealing
12th Nov 20259:30 amRNSPDMR Dealing
10th Nov 20257:00 amRNSNotice of Annual General Meeting
6th Nov 202510:13 amRNSSale of Asiamet’s Interest in the KSK Project
6th Oct 202510:00 amRNSLong Term Incentive Programme
17th Sep 20257:00 amRNSDirector’s Fees and Employee Share-Based Payments
15th Sep 20257:00 amRNSBKM Copper Project Limestone Drilling Update
29th Aug 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
15th Aug 20257:00 amRNSLimestone Resource Drilling at BKM Copper Project
11th Aug 20257:00 amRNSAppointment of Project Director for BKM
18th Jul 20257:00 amRNSAppointment of Grant Samuel
15th Jul 20254:00 pmRNSCompletion of Subscription
9th Jul 20257:00 amRNSAppointment of Shore Capital as Corporate Broker
9th Jun 20255:15 pmRNSTR-1: Notification of major holdings
5th Jun 20257:00 amRNSCommencement of BKM Project Financing Process
29th May 20257:21 amRNSUS$2.5 million Subscription
29th May 20257:07 amRNS2024 Annual Report & Financial Statements
20th May 20257:00 amRNS-RBKM Stage 1 OFS – Investor Presentation and Q&A
15th May 20257:00 amRNSCompletion of BKM Feasibility Study ITE Report
7th May 20257:00 amRNSBKM Copper Project Optimised Feasibility Study
2nd May 202512:15 pmRNSUpdated Ore Reserve for BKM Stage 1
24th Apr 20257:00 amRNSPower Study Completes Inputs for Feasibility Study
28th Mar 20257:00 amRNSBKM Optimised Feasibility Study Near Completion
23rd Dec 20243:00 pmRNSBKM Capital Cost Estimate Reduced by US$58 Million
17th Dec 202410:00 amRNSDirector’s Fees and Employee Incentive Payments
26th Nov 202411:30 amRNSAppointment of Head of Corporate Finance
14th Nov 20247:00 amRNSBKM Copper Project Optimisation Works Update
18th Oct 20245:00 pmRNSSuccessful Completion of US$3.55 million Raise
15th Oct 20242:30 pmRNSRetail Offer
15th Oct 20242:25 pmRNSUS$3.3 million Subscription
7th Oct 20247:05 amRNSBoard Changes
30th Sep 202412:00 pmRNSInterim Results for Six Months Ended 30 June 2024
22nd Aug 202411:30 amRNSMaterial Capex Reductions for BKM Copper Project
26th Jun 20244:30 pmRNSResult of AGM
25th Jun 20247:00 amRNSBKM Copper Project Optimisation
3rd Jun 202410:00 amRNSNotice of Annual General Meeting
14th May 20247:00 amRNSBKM Heap Leach Facility Earthworks Optimisation
9th May 202411:45 amRNS2023 Annual Report & Financial Statements
17th Apr 20247:00 amRNSBKM High Grade Copper Rock Sample Results
28th Mar 20247:00 amRNSBKM Project Engineering Design & Execution Update
27th Mar 20247:00 amRNSSustainable Power Solution for BKM Copper Project
1st Mar 20247:04 amRNSCorporate Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.