Public infrastructure upgrades improve BKM project

19 Sep 2019 07:00

RNS Number : 9246M
Asiamet Resources Limited
19 September 2019
 

 

19 September 2019

 

Public infrastructure upgrades improve BKM project transport and logistics

 

Asiamet ("ARS" or the "Company") is pleased to announce that a number of recent government infrastructure initiatives and planned upgrades to bridges and roads within Central Kalimantan is expected to significantly improve transport and logistics options for the BKM Copper project and result in reduced operating costs relating to the transport of supplies in and copper cathode out of the proposed BKM mine site.

Post completion of the BKM feasibility study, the Company is currently reviewing a number of options and alternatives to add significant further value to the BKM copper project, (as announced on 14 June 2019). The assessment of planned public infrastructure works was undertaken as part of these value enhancement studies.

A review of the logistics and transport section of the study yielded some potential high value alternatives, one being the use of the Bagendang Port (Sampit Port) compared with the Banjarmasin Port used in the BKM Feasibility Study. Recent infrastructure initiatives and planned upgrades to government bridges and roads have now allowed the study team to review this alternative route as a preferred logistical hub.

This revised option would result in:

·; a more efficient turnaround time for the transport of supplies and copper cathode in and out of site.

·; a saving of approximately 140 kilometres per one way trip or 280 kilometres per round trip. The distance from the BKM site to Banjarmasin Port is approximately 495 kilometres compared with approximately 350 kilometres from site to the Sampit Port. A map comparing the two logistical routes is shown in Figure 1.

·; improvement in project operating costs by several millions of dollars over the initial life of mine due to the shorter logistics distance. As the detailed costings are finalised the outcomes will be reported.

The Sampit Port as shown in Figure 2, is an established container terminal for smaller vessels and cargo and would suit the operations of the BKM project. Included in recent upgrades is a major new bridge being constructed at Samba as per Figure 3 below.

 

Peter Bird, Asiamet's CEO commented:

"Following completion of the BKM Feasibility Study the Asiamet team has continued to focus on further enhancing the value of the BKM Copper project through the assessment of a number of opportunities identified and reported on as part of the study. The refinement of the logistics route to Sampit Port and the associated reduction in operating costs over the life of mine is an excellent example of the value expected to be delivered from this process. Our team along with our technical service providers are systematically working through the 15 identified opportunities and expect to report further positive results as they come to hand.

The BKM Copper project remains one of the most advanced copper projects in Asia at a time when global mine supply is forecast to move into deficit. The delivery of a robust Feasibility Study and the opportunity for further significant upside through value engineering and exploration has increased awareness of the BKM project amongst a number of strategic investors and potential partners with whom discussions are continuing."

 

Figure 1 Insert Map of site to Banjarmasin Port and Bagendang Port. To view the image, click on the link below http://asiametresources.com/assets/img/ars_1_180919.png 

Figure 2 Bagendang Port in Sampit. To view the image, click on the link below http://asiametresources.com/assets/img/ars_2_180919.png

Figure 3 Bridge Construction at Samba. To view the image, click on the link below http://asiametresources.com/assets/img/ars_3_180919.png

 

Value Enhancement Program - Background details

The Value Enhancement (VE) program was reported in the Feasibility Study for the BKM project (announced 14 June 2019). This process identified and ranked 20 opportunities ranging in value delivery and ease of implementation. These VE opportunities were risk adjusted and totalled an estimated $35M (excludes exploration success) in additional value that can be added to the BKM project value. Larger impact initiatives include:

·; pre-treatment of the currently discarded, less-leachable heap leach ore types such as chalcopyrite by utilising the Albion Leaching technology (~$20M);

·; improved mineralisation geological controls by incorporating detailed structural geology model (~$5M);

·; an electricity supply scope change from gas supply to local coal supply (~$4M);

·; further refining the methodology of ore block classification to enhance metal and commercial returns (~$3.5M);

·; reducing construction earthworks costs by sourcing locally and delivering synergies by working with the mining contractor (~$3M); and

Over and above these VE initiatives, review of near mine exploration for targets proximal (less than 3km) to the BKM Resource that have the potential to add significant value was also considered. These targets may add treatable copper resources to that already defined or create further opportunities for revenue enhancement through direct shipping of ore. The high priority targets to be investigated immediately include:

·; BKM 'link zone target' the immediate zone between BKM and BKZ;

·; Testing of IP chargeability highs approximately 800m to the north-west if BKM;

·; BKM depth extensions through deeper drilling to follow up IP chargeability at depth; and

·; BK-South near surface oxide targets, maybe amenable to SX-EW process and augment the current mine life at BKM.

The Company has completed and lodged all required documentation in relation to the permits required for exploration access of the abovementioned targets and mobilisation of drilling equipment is anticipated in early-mid Q4 2019.

 

 

ON BEHALF OF THE BOARD OF DIRECTORS

Peter Bird, Deputy Chairman and CEO

For further information, please contact:-Ends-

 

Peter BirdDeputy Chairman and CEO, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: peter.bird@asiametresources.com

 

Tony ManiniExecutive Chairman, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: tony.manini@asiametresources.com

 

FlowComms Limited

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: Sasha@flowcomms.com 

Asiamet Resources Nominated AdviserRFC Ambrian Limited

Andrew Thomson / Stephen Allen

Telephone: +61 8 9480 2500

Email: Andrew.Thomson@rfcambrian.com / Stephen.Allen@rfcambrian.com 

 

Berenberg

Matthew Armitt, Detlir Elezi

Telephone: +44 20 3207 7800

Email: Matthew.Armitt@berenberg.com / Detlir.Elezi@berenberg.com 

 

LiberumClayton Bush, Kane Collings

Telephone: +44 7773 322679

Email: Clayton.Bush@liberum.com 

 

Optiva Securities LimitedChristian Dennis

Telephone: +44 20 3137 1903

Email: Christian.Dennis@optivasecurities.com

 

Follow us on twitter @AsiametTweets

This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterised by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices. There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
UPDEKLBFKKFLBBB
Date   Source Headline
7th Aug 20187:15 amRNSDrilling Extends Beutong Copper Mineralisation
19th Jul 20184:30 pmRNSExercise of Options
12th Jul 20188:03 amRNSAppointment of Executive VP - External Relations
2nd Jul 20186:00 pmRNSExercise of Options and Warrants - Replacement
2nd Jul 201812:40 pmRNSExercise of Options and Warrants
26th Jun 20187:00 amRNSAppointment of Director
25th Jun 201810:30 amRNSResult of AGM
25th Jun 20187:00 amRNSLifts Beutong Copper-Gold Project Interest to 80%
22nd Jun 201810:57 amRNSAttendance at Mining Journal Select Conference
14th Jun 201810:21 amRNSIntersects 456m of Cu mineralisation at Beutong
6th Jun 201812:00 pmRNSExercise of Options
1st Jun 201811:45 amRNSDirector Appointment
25th May 20185:00 pmRNSNotice of Annual General Meeting
24th May 20188:00 amRNSDirector Changes
16th May 20187:00 amRNSInitial Mineral Resource Estimate for BKZ Deposit
2nd May 20182:30 pmRNSExercise of Options
27th Apr 20189:00 amRNS2017 Annual Report & Financial Statements
18th Apr 20183:30 pmRNSBroker Warrants Exercised
16th Apr 20183:10 pmRNSAsiamet April Investor Events - Birmingham, London
16th Apr 201811:15 amRNSIntersects High Grade Mineralisation at Beutong
3rd Apr 201811:19 amRNSReports BKM Geotech Results - Replacement
3rd Apr 20187:30 amRNSReports Assay Results for BKM Geotech Holes
29th Mar 20185:00 pmRNSExercise of Options
28th Mar 201810:25 amRNSBKZ Delivers Outstanding Mineralisation
26th Mar 20189:35 amRNSSecures long term tenure for BKM Copper Project
19th Mar 201812:49 pmRNSBKZ Drilling Intersects High Grade Mineralisation
13th Mar 20186:15 pmRNSSuccessful Placing of £7.2 Million
13th Mar 201812:15 pmRNSPlacing to Raise up to £7.2 Million
9th Mar 201810:30 amRNSExercise of Options
1st Mar 201812:00 pmRNSCorporate Broker Appointment
1st Mar 20187:30 amRNSCommences Drilling Beutong Copper-Gold Deposit
28th Feb 20187:20 amRNSmetallurgical tests confirm positive results
22nd Feb 20181:35 pmRNSIntersects Further High-Grade Zinc, Lead, Copper
13th Feb 20181:00 pmRNSExercise of Options
6th Feb 20187:00 amRNSIntersects High Grade Copper Mineralisation at BKZ
31st Jan 20187:00 amRNSBKZ Delineation Drilling and Plans for Beutong
17th Jan 201811:45 amRNSDirector Resignation
11th Jan 201811:15 amRNSGrant of Options
11th Jan 20189:15 amRNSCommences Resource Drilling at BKZ
8th Jan 20187:00 amRNSProduction Licence for Beutong Project
19th Dec 201710:15 amRNSPositive Metallurgical Test-work Results
29th Nov 20177:00 amRNSIntersects 115.5m at 1% Cu at BK44 Zone
24th Nov 201712:15 pmRNSAppointment of James Deo as CFO
21st Nov 201712:15 pmRNSFurther High-Grade Zn-Pb-Ag at BKZ Deposit
13th Nov 20178:40 amEQSAsiamet Extends High Grade Copper Mineralisation Beneath BKZ Zn-Pb-Cu-Ag-Au Deposit
1st Nov 201711:32 amEQSAsiamet Intersects High Grade Copper Below BKZ Polymetallic Deposit
25th Oct 20177:02 amEQSAsiamet Appoints Ausenco
20th Oct 20179:02 amEQSAsiamet Resources Ltd.: Broker Warrants Exercised
18th Oct 20177:02 amEQS30m of 8.3% Zinc at BKZ and Extends High Grade Polymetallic Discovery
11th Oct 20177:02 amEQSExceptional Zn-Pb-Ag-Au Drill Results Upgrade Potential of BKZ Discovery

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.