BKM Copper Project BFS Update

18 Dec 2018 08:13

RNS Number : 8012K
Asiamet Resources Limited
18 December 2018
 

BKM Copper Project BFS Update

Asiamet Resources is pleased to advise that the 4,500 metre Resource infill and geotechnical drilling program being undertaken to enhance the Beruang Kanan Main Copper Project ("BKM" or "the project") bankable feasibility study ("BFS") is well underway with initial results anticipated shortly.

As previously announced, the planned drilling and associated study program aims to better optimise the mine design and improve the overall economics and robustness of the Bankable Feasibility Study (BFS) for the BKM copper project in preparation for project financing.

A small group of highly experienced resource, geotechnical and mine engineering consultants were re-engaged in early November to oversee the collection, integration and interpretation of the additional data required to supplement current studies. Along with these technical consultants an external drilling contractor has also recently been engaged to fast-track the drilling program.

Asiamet's own two fully-owned drill rigs were mobilised during late November with a total of four holes (494.6 metres) completed to 15 December 2018. Core samples have been sent to laboratories for assaying and a further three drill holes are in progress.

In order to expedite the current drill programme, an additional two rigs have been sourced from an external contractor with significant prior experience on the BKM project. Drills have been mobilised to site and will commence drilling shortly.

Initial drilling is focussed on two key mineralised zones within and as extensions of the current open pit design as shown in Figure 1 linked below, where an upgrade in Resource confidence from the Inferred category to the Indicated and Measured category (JORC 2012) is targeted.

Resources upgraded in the current drill program will then be economically assessed for potential conversion to Ore Reserves. Increasing Ore reserves available for integration into mine planning and design optimisation studies is expected to increase mine life and enhance overall robustness of the project from a financing perspective.

Link to image of Proposed BKM pit shell with proposed zones for drilling: http://asiametresources.com/assets/img/ars2_171218.png

Corporate

In early December, meetings were held with a number of potential strategic investors and partners in Jakarta. The level of interest in Asiamet's portfolio of assets remains high and several groups have signed confidentiality agreements and are actively engaged in technical due diligence. Discussions with several other parties are continuing with a view to upscaling diligence activity early in the new year.

 

Peter Bird, Asiamet's Chief Executive Officer commented:

"Despite the general poor market sentiment for exploration and development companies at present, Asiamet believes that it's portfolio of high-quality assets is significantly undervalued and the Company remains extremely focussed on progressing the infill and geotechnical drilling programs required to enhance the economic robustness of the BKM BFS at a time of compelling near term supply-demand fundamentals for copper.

This additional piece of study work is expected to significantly enhance the robustness of the BKM copper project and positively impact outcomes from both a project financing and strategic partnering perspective. We look forward to providing results and further updates from the drilling and study program as the work programs progress over the coming weeks"

 

ON BEHALF OF THE BOARD OF DIRECTORS

Peter Bird, Deputy Chairman and CEO

For further information, please contact:

-Ends-

Peter BirdDeputy Chairman and CEO, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: peter.bird@asiametresources.com

 

Tony ManiniExecutive Chairman, Asiamet Resources LimitedTelephone: +61 3 8644 1300Email: tony.manini@asiametresources.com

 

FlowComms Limited

Sasha Sethi

Telephone: +44 (0) 7891 677 441

Email: Sasha@flowcomms.com

Asiamet Resources Nominated Adviser

RFC Ambrian Limited

Andrew Thomson / Stephen Allen

Telephone: +61 8 9480 2500

Email: Andrew.Thomson@rfcambrian.com / Stephen.Allen@rfcambrian.com 

 

Berenberg

Matthew Armitt, Sara MacGrath

Telephone: +44 20 3753 3142

Email: Matthew.Armitt@berenberg.com

 

Liberum

Clayton Bush, Kane Collings

Telephone: +44 7773 322679

 

Optiva Securities Limited

Christian Dennis

Telephone: +44 20 3137 1903

Email: Christian.Dennis@optivasecurities.com

 

This news release contains forward-looking statements that are based on the Company's current expectations and estimates. Forward-looking statements are frequently characterised by words such as "plan", "expect", "project", "intend", "believe", "anticipate", "estimate", "suggest", "indicate" and other similar words or statements that certain events or conditions "may" or "will" occur. Such forward-looking statements involve known and unknown risks, uncertainties and other factors that could cause actual events or results to differ materially from estimated or anticipated events or results implied or expressed in such forward-looking statements. Such factors include, among others: the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; possible variations in ore grade or recovery rates; accidents, labour disputes and other risks of the mining industry; delays in obtaining governmental approvals or financing; and fluctuations in metal prices. There may be other factors that cause actions, events or results not to be as anticipated, estimated or intended. Any forward-looking statement speaks only as of the date on which it is made and, except as may be required by applicable securities laws, the Company disclaims any intent or obligation to update any forward-looking statement, whether as a result of new information, future events or results or otherwise. Forward-looking statements are not guarantees of future performance and accordingly undue reliance should not be put on such statements due to the inherent uncertainty therein.

 

This announcement contains inside information as stipulated under the Market Abuse Regulations (EU) no. 596/2014 ("MAR").

 

 

 

 

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.
 
END
 
 
DRLVVLBFVLFFFBF
Date   Source Headline
26th May 20265:30 pmRNS2025 Annual Report & Financial Statements
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
12th Mar 20267:25 amRNSRegulatory Approval Received for KSK Transaction
29th Jan 20261:30 pmRNSResults of General Meeting
27th Jan 20265:30 pmRNSUpdate on Proposed Sale of Indokal (KSK Project)
17th Dec 20256:08 pmRNSUS$3.1 million Subscription
9th Dec 20251:55 pmRNSResults of Annual General Meeting
27th Nov 202512:45 pmRNSPDMR Dealing
14th Nov 202510:00 amRNSPDMR Dealing
12th Nov 20259:30 amRNSPDMR Dealing
10th Nov 20257:00 amRNSNotice of Annual General Meeting
6th Nov 202510:13 amRNSSale of Asiamet’s Interest in the KSK Project
6th Oct 202510:00 amRNSLong Term Incentive Programme
17th Sep 20257:00 amRNSDirector’s Fees and Employee Share-Based Payments
15th Sep 20257:00 amRNSBKM Copper Project Limestone Drilling Update
29th Aug 20257:00 amRNSInterim Results for Six Months Ended 30 June 2025
15th Aug 20257:00 amRNSLimestone Resource Drilling at BKM Copper Project
11th Aug 20257:00 amRNSAppointment of Project Director for BKM
18th Jul 20257:00 amRNSAppointment of Grant Samuel
15th Jul 20254:00 pmRNSCompletion of Subscription
9th Jul 20257:00 amRNSAppointment of Shore Capital as Corporate Broker
9th Jun 20255:15 pmRNSTR-1: Notification of major holdings
5th Jun 20257:00 amRNSCommencement of BKM Project Financing Process
29th May 20257:21 amRNSUS$2.5 million Subscription
29th May 20257:07 amRNS2024 Annual Report & Financial Statements
20th May 20257:00 amRNS-RBKM Stage 1 OFS – Investor Presentation and Q&A
15th May 20257:00 amRNSCompletion of BKM Feasibility Study ITE Report
7th May 20257:00 amRNSBKM Copper Project Optimised Feasibility Study
2nd May 202512:15 pmRNSUpdated Ore Reserve for BKM Stage 1
24th Apr 20257:00 amRNSPower Study Completes Inputs for Feasibility Study
28th Mar 20257:00 amRNSBKM Optimised Feasibility Study Near Completion
23rd Dec 20243:00 pmRNSBKM Capital Cost Estimate Reduced by US$58 Million
17th Dec 202410:00 amRNSDirector’s Fees and Employee Incentive Payments
26th Nov 202411:30 amRNSAppointment of Head of Corporate Finance
14th Nov 20247:00 amRNSBKM Copper Project Optimisation Works Update
18th Oct 20245:00 pmRNSSuccessful Completion of US$3.55 million Raise
15th Oct 20242:30 pmRNSRetail Offer
15th Oct 20242:25 pmRNSUS$3.3 million Subscription
7th Oct 20247:05 amRNSBoard Changes
30th Sep 202412:00 pmRNSInterim Results for Six Months Ended 30 June 2024
22nd Aug 202411:30 amRNSMaterial Capex Reductions for BKM Copper Project
26th Jun 20244:30 pmRNSResult of AGM
25th Jun 20247:00 amRNSBKM Copper Project Optimisation
3rd Jun 202410:00 amRNSNotice of Annual General Meeting
14th May 20247:00 amRNSBKM Heap Leach Facility Earthworks Optimisation
9th May 202411:45 amRNS2023 Annual Report & Financial Statements
17th Apr 20247:00 amRNSBKM High Grade Copper Rock Sample Results
28th Mar 20247:00 amRNSBKM Project Engineering Design & Execution Update
27th Mar 20247:00 amRNSSustainable Power Solution for BKM Copper Project
1st Mar 20247:04 amRNSCorporate Update

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.