Company update

30 Oct 2009 07:00

Watermark Global Plc("Watermark" or the "Company")Completion of the Definitive Feasibility Study

Watermark, the AIM quoted Company which focuses on the treatment of Acid Mine Drainage (AMD) in South Africa, is pleased to announce that the Definitive Feasibility Study ("DFS") being conducted by its wholly owned subsidiary, Western Utilities Corporation (Pty) Ltd., ("WUC") has now been completed.

The DFS was led by independent consultants, Golder Associates, together with a number of engineering and environmental specialists. It was completed within the original budget of R35million and its results confirm the project's viability in five main areas: (1) the verification and securing of AMD for treatment; (2) the selection, design and costing of the scheme; (3) the completion of the Integrated Regulatory Process; (4) the signing of a binding off-take agreement; (5) the economic and financial analysis of the project.

Highlights

Validation of the projects' viability Total capital cost for the project of R1.5 billion Small delay in expected commencement of construction which is now anticipated to be in second quarter 2010 with commissioning in 2011. This timeline dependent on water off take agreement with Rand Water and funding of the project. Watermark is now well-placed to complete its negotiations with Rand Water by year end Negotiations with Black Economic Empowerment ("BEE") partners are also expected to be finalised shortly Final approval of the Environmental Impact Assessment ("EIA"), is expected by February 2010

Jaco Schoeman, CEO of Watermark, commented:

"We are delighted to be able to report the completion of the DFS. It has been an incredibly complicated task and I would like to pay tribute to my colleagues and all the other parties involved - we now have a building block for future progress. With the DFS, we can complete our agreement with Rand Water and add further impetus to our project. Negotiations with our BEE partners are continuing and a draft shareholders agreement at WUC level is being discussed. Procuring BEE participation will assist with the Integrated Regulatory Process, and also add valuable local participation to the project. Further updates on the various aspects of the project will be provided over the coming weeks."

Resource Verification

As was previously announced, the total volume of AMD available for treatment, as verified by Golder Associates is 155 Mega Litres (ML) per day of which, on average, 67 ML will be treated to industrial water standards for consumption by the mines participating in the project, while the rest (on average 88ML/day) will be treated to drinking water standards (South African Bureau of Standards 241) and sold to bulk water distributors, such as Rand Water.

Selection, Design and Costing of the Total Scheme

The total scheme incorporates the collection of AMD water from the three basins, namely the Western, Central and Eastern Basins, the treatment of the water at a centralised plant, and the distribution of the water back to the mines and to bulk water suppliers in the region such as Rand Water.

The centralised water treatment plant design is based on the Alkali-, Barium-, Calcium- process developed by the Council for Scientific and Industrial Research in which WUC has secured a 20% participation in the Intellectual Property during the development of the process.

The Integrated Regulatory Process ("IRP")

The IRP focuses on the completion of the Environmental Impact Assessment ("EIA") for the entire scheme. Approval of the Final Scoping Report was delayed by the Gauteng Department of Agriculture and Rural Development (GDARD) by a month and approval is finally due to be received by the 30th of October 2009. Following this we expect to submit the Environmental Impact Report for public review by the 15th of November. Following a 30 day public comment period the EIA will be submitted to the relevant authorities and the final Record of Decision (RoD) is expected to be received by the 15th of February 2010 assuming no further delays from the South African Government. The delay in the approval of the Final Scoping Report has had a direct impact on the timelines of the project and, as a result, may delay the start of construction.

The IRP includes the application for an Integrated Water Use License. This application must be supported by the EIA and will be submitted together with the EIA to the relevant authorities. Approval will only be granted once the RoD has been issued. A number of discussions have been held with the relevant authorities and the Board believes that the approval of the IWULA will not be unnecessarily delayed.

Rand Water off-take Agreement

In order for WUC to negotiate an economically viable selling price for the drinking water it was necessary to complete the Definitive Feasibility Study. which included capital and operating cost estimates. Certain assumptions have been made in the financial model and Feasibility Study to ascertain this selling price and the Board believes that this will be achievable. A final agreement has not yet been reached and as previously announced a formal agreement is expected by December 2009.

Financial and Economic Analysis of the project

The total estimated capital cost of the scheme amounts to approximately R1.52bn, excluding fees and financing costs. The capital and operating cost estimates are within ±15%. Cost estimates are based on the engineering designs completed for each of the components of the scheme either through formal tenders (collection and distribution systems), formal quotes and or standard engineering practice estimates. Preferred suppliers have been selected and contract negotiations will follow the securing of funds. The following table provides an overview of the costs for the various aspects of the scheme:

Scheme Component

ZAR million

Collection system 275.45
Treatment Plant 968.46
Distribution system 225.51
Other 52.18
Total Project Cost 1 521.6

With the negotiations for the off-take still in progress, the Directors believe that it would be inappropriate to release any rates of return figures at this time. However a commercially attractive rate is the minimum starting point for our discussions. Certain assumptions have been made with regard to the selling prices of water and a pricing strategy has been developed. A full financial analysis will only be released once the negotiations with Rand Water have been completed due to the sensitivity and confidentiality of the information during the negotiation process. Operating costs for the plant have been defined in great detail and an expert third party review of these costs was completed as part of the study.

Looking Forward

With the delays in the EIA approval process and completion of the Rand Water off-take agreement, it is now expected that construction of the plant will commence in the second quarter of 2010 with the plant being ready for commissioning in 2011. The timeline is also dependent on the finalisation of the funding structure of the project, which is expected by March 2010.

Enquiries:

Watermark Global
Dirk Kotze, Chief Financial Officer Tel: + 44(0) 20 7233 1462

dkotze@watermarkglobalplc.com

Charles Zorab, Investor Relations Tel: + 44(0) 20 7233 1462

czorab@watermarkglobalplc.com

Nominated Adviser
Cenkos Securities
Ian Soanes/Elizabeth Bowman Tel: +44(0) 20 7397 8900
Financial PR
Bishopsgate Communications
Robyn Samuelson/Giang Nguyen Tel: +44(0) 207562 3355

Copyright Business Wire 2009

Date   Source Headline
21st Feb 20207:00 amBUSProject Update
17th Jan 20207:00 amRNSExercise of Warrants and Issue of Equity
7th Jan 202011:01 amBUSAppointment of Non-executive Director
27th Dec 20191:00 pmBUSREPLACEMENT: Exercise of Warrants and Issue of Equity
23rd Dec 20191:45 pmBUSExercise of Warrants
18th Dec 201912:00 pmBUSCorporate Update
6th Dec 20197:00 amRNSAppointment of Non-executive Director
26th Nov 20198:25 amBUSDirectorate change
11th Nov 20199:25 amBUSMine Design & Project Engineer Site Visit Update
1st Nov 201910:36 amRNSFurther Information on Strategic Financing
30th Oct 201910:15 amBUSFurther Strategic Financing
25th Oct 20199:40 amBUSFurther Offtake Agreement MOU
18th Oct 20197:00 amRNSShareholder Webinar
15th Oct 20199:40 amBUSResource Upgrade Confirms High Grade Near Surface Mineralisation
3rd Oct 20197:00 amRNSNew Corporate Presentation
26th Sep 20197:00 amBUSFurther Offtake Agreement MOU
25th Sep 20192:20 pmRNSInvestor Presentation Evening
16th Sep 20191:41 pmBUSStrategic Financing
16th Sep 201911:14 amBUSInterim Results
11th Sep 20197:00 amBUSMineral Resource Update Nearing Completion
5th Sep 20192:00 pmRNSPrice Monitoring Extension
4th Sep 201911:30 amBUSDownstream Test-Work Commenced
28th Aug 20197:04 amBUSHigh-Grade Assay Results Demonstrate Commercial Potential of Large Graphite Project
22nd Aug 20197:45 amBUSMetallurgical Test-work Completes with Highly Encouraging Results
8th Aug 20197:00 amBUSExceptionally High Purity – Metallurgical Test-work
16th Jul 20197:00 amBUSPositive Metallurgical Test-Work Results
27th Jun 201912:15 pmBUSResult of AGM
27th Jun 20197:00 amBUSAGM Statement
25th Jun 20197:00 amBUSExceptionally High-Grade Assay Results
3rd Jun 20193:00 pmBUSDirector Share Purchase
29th May 201910:15 amBUSFast-tracking Commercialisation Plans
28th May 20197:00 amBUSFinal Results and Notice of AGM
20th May 201910:45 amBUSNew Corporate Presentation
15th May 20197:00 amBUSMahenge Liandu Project DFS Update
26th Apr 20197:00 amBUSMahenge Liandu Graphite Project DFS Update
16th Apr 20197:45 amBUSMahenge Liandu Graphite Project Update
20th Mar 201910:53 amRNSHolding(s) in Company
11th Mar 20197:00 amBUSAppointment of Non-executive Director
27th Feb 201910:15 amBUSStrategic Financing & Corporate Update
19th Feb 20197:00 amBUSMOU Signed for Mahenge Liandu Graphite Project
11th Jan 20197:00 amBUSFormal Agreement Reached for the Sale of the non-core Mpokoto Gold Project
24th Oct 20189:08 amBUSProposed Sale of the non-core Mpokoto Gold Project
21st Sep 20187:00 amBUSAppointment of Marketing Consultant
20th Sep 20187:00 amBUSInterim Results
21st Jun 20183:33 pmBUSResult of AGM
6th Jun 20187:00 amBUSReserve Definition Drilling Commences at Mahenge Liandu Graphite Project
23rd May 20187:00 amBUSFinal Results
21st May 20184:00 pmBUSChange of registered address
3rd May 20187:00 amBUSCommencement of Feasibility Study at Mahenge Liandu
9th Apr 201811:00 amBUSPlacing to Raise £963,500

Due to London Stock Exchange licensing terms, we stipulate that you must be a private investor. We apologise for the inconvenience.

To access our Live RNS you must confirm you are a private investor by using the button below.