RE: Phase 2 of SL16 Jan 2026 17:43
So here are my thoughts on the timing of Phase 2;
Given the delay in announcing FID, I think we can now presume that the timings given in the EIS are likely to slip by a similar amount.
In any case, now that they have the Rig and main Contract packages sorted out, the Drilling & Completions people will be able to go into much greater detail in well timings, as they can now factor in how long it takes the Rig to perform a particular operation (e.g. Running BOP's, running casing etc).
They'll also get with the contractors to do a similar exercise, e.g. how long it takes to put each BHA together, how long to run the Completion, set up and perform the gravel pack etc,
Similarly, I'm willing to bet that when they did the timing for the EIS, they didn't yet have the bottom hole locations for each Well, so the individual Well directional programs couldn't be factored in.
But sticking with their base case, which appears to be 500 Days to drill and complete all the Wells, this gives the following timing;
1st March 2027 - Commence drilling the first SL Well
July 2028 - Complete drilling the last Well on Phase 1
Currently it looks like 1st Oil will be somewhere around Q2 2028.
For SL Phase 2, they should be able to roll over the major equipment supply contracts rather than having to re-tender everything, so that means they'll need 18 months lead time to order and transport everything down to PS.
To avoid an extended period where the Rig is potentially idle, they would need to get to FID for Phase 2 in December 2026 so they can order the equipment in January 2027 - long before 1st Oil.
That brings up two issues; are they confident enough in their reservoir modelling to order the Phase 2 equipment before they have any production data to validate their models and can RKH fund our share of any cash calls?
The second point is the easy one - at the moment, we do not.
Now, much of the equipment would be pretty standard and easily sold on in the event of project failure - but they'd still only get, say, 50% of what was paid. Some of it is not, like the Vacuum Insulated Tubing and it would be questionable if the sand screens could be sold on.
Could a potential OM award cover the costs? Even if we did get awarded the cash on appeal, it would still be too late and in any case, wouldn't cover our share of the Phase 2 costs.
With respect to the first point, a good case could be made that ordering upfront and potentially taking a hit if it all goes tits up would be less than the guaranteed $10's Millions it would cost to demob the rig and equipment, only to have to mob it all again 18-24 months later.
However, Oil Co's are notoriously conservative and here we don't have any offset production information to use as a 'go-by', so I'm leaning towards FID Phase 2 in Q4 2028 with drilling commencing in Q1 2030 - which RKH could fund from SL cash flow.