Estimate 2025 drill duration / results etc28 Jul 2025 17:41
Project Drilling Start Est Drilling Duration Drilling Complete Results Primary Targets
Verkhuba Q2 2025 (ongoing) 6–8 weeks ~Late July 2025 Aug–Sep 2025 Aug/Sept Cu, Zinc (Zn), Lead (Pb) – VMS
Talovskoye Late May–Early Jun 6–8 weeks ~Late July 2025 Sep–Oct 2025 Sept/Oct Cu, Pb, Zn, Ag, Au – High-grade VMS target
Rulikha June–July 6–8 weeks ~ August 2025 Sep–Oct 2025 Sept/Oct Cu, Zn, Au, Ag
Snowy Not yet started (Q4?) TBC – ~4–6 weeks (first-pass) Poss Dec 2025 Early 2026 Au–Ag & Cu–Mo porphyry anomalies