RE: 0.609 Mar 2022 09:48
Guys, I really think that there is no issue here. These “new” elements are not new, I believe that is the confusion here is the vague way it is worded.
There have been some changes to the layout brought about buy HSE review, we know about these - flare height, relocation of generators, etc.
I think the Plot Plan had errors in it which have now been corrected.
- Firewater tank - was always needed
-Condensate Stabilisation Tower - was in from day 1, is described in a document I read months ago
- Condensate and Oily Water Banded Storage Area - We saw these tanks being tested/painted, where in from Day 1
- Air Coolers - they are already on site, we saw the tweets
Looks like all documentation is being aligned. No probs.