RE: 1 days diference!14 Mar 2022 16:12
Howey/ SillyButtons,
In my opinion, bar an unforeseen issue and I cannot think of any apart from PP/EA approvals, we now have a defined path to production by end of May. It is all in the update RNS.
Complete civil works by the end of March. All foundations will be completed and the packages/equipment can be sited on them as they arrive.
Cable lay/pull late March / early April and connect to the equipment as they arrive.
Connect and pre-commission equipment as they arrive.
Installation of pipework is already ongoing. Sections of pipework can be tested as they are progressing.
Late equipment are the two packages, J-T skid arriving 24th April and Condensate Stabilisation Skid arriving 29th April. Two weeks connect and pre-commission and complete overall integration.
Let the gas in (First Gas) mid-May, finish hot commissioning and testing another 2 weeks.
Full production by end of May.
Is doable.