RE: Warrants to regret?22 Sep 2022 16:54
BV, tbh, the issue with the compressors is a bit confusing to me but I didn’t give it much thought.
The process flow diagram submitted to the EA/NSTA shows a requirement for two compressors - 1st stage gas compressor before the dehydration package, and, a 2nd stage gas compressor after the J-T package and this makes sense to me. However, GL said there is only one compressor installed at site I think and this would mean a design change and removal of the second stage. But, GL referred to 3 compressors. Note that there is space for a third Booster Compressor to be used in the future when the well pressure drops. So, I don’t really know what is really happening with the compressors, not without looking at a Piping & Instrumentation Diagram.
Anyway, I am not concerned. As GL said in an answer to an IQ that all compressors are sized for 10 MMSCFD.
Adding another compressor in the system though, will definitely require a shutdown and I don’t think we want this now, seen the problems with start up. Let’s get some cash in first :)