The equipment will be rigged-up over a period of one to two weeks prior to drilling operations commencing. The borehole will be drilled to an approximate depth of 2,000 metres and is expected to take six to ten weeks to complete. Drilling will continue 24 hours a day. Once completed, the drilling rig will be demobilised from the site over a period of approximately one week.
...and we have Wressle to look forward to, plenty of newsflow. "first oil", expected during H2 2020.