Bushveld Energy Q1 Operational Update
Wed, 11th Apr 2018 08:30
RNS Number : 5418K
Bushveld Minerals Limited
11 April 2018
Eskom VRFB project
· Completed manufacturing of the Direct Current ("DC") portion of the VRFB, with factory acceptance expected in April 2018 and delivery of the entire system still on track in the second quarter of this year;
· Commenced site preparation work at the Eskom site, including earthworks and cabling;
· Appointed two technicians from South Africa to perform installation and maintenance on the Eskom project. Technicians will be training at UniEnergy Technologies, a US-based leading VRFB manufacturer, in April. This will give Bushveld Energy the capability to install and maintain future VRFB installations in South Africa and regionally.