A6, A8, 801 to be completed by end of april30 Mar 2020 11:16
It's worth remembering that A6, 801 & A8 will be completed by end of April. Each could produce between 1000 - 3000 bopd of oil per day. By the beginning of may we could be producing and additional 3000 - 9000 bopd. In addition to our 1800 bopd currently. That means our production will be at 4800 - 9800 bopd per day, nearly 4 times our current amounts. I can see it doing a re-rate even at current oil prices as we are a low cost producer, if the oil price goes up that just a bonus.
Following acid treatment which roughly takes 3 days per well, the wells will be put into production immediately.
"For the avoidance of doubt the existing producing wells will continue to be operated and the production sold, as will the New Wells 150 & 153 as they come into production, and as will any of the three Deep Wells that flow following the acid treatment referred to above."