Consider this for a minute. The FY operational update for period ended 28 Feb 2025 RNS of 31st. March said the following: -
Ore processed 965,058 tonnes
Feed grade 0.137%
Tin recovery 72%
Tin metal produced full year 932 tonnes.
If you substitute the feed grade for the high-grade ore that’s coming from Goantagab but the amount of ore processed and tin recovery figures remain the same you get this: -
Ore processed 965,058 tonnes
Feed grade 1.5%%
Tin recovery 72%
Tin metal produced, full year 10,422.6 tonnes.
And that’s based on the existing jig plant not the second one currently being assembled that will add 100 tph processing rate (current plant 136 tph).
I know the high-grade ore supply deal will take a fair bit of the cream in the early years but the potential here is enormous for those with the time and patience to wait.