RE: $6,0000/oz25 Jul 2025 15:41
Rhodium up a further 5% in the past two days to $6,350/oz
The average basket price peaked midweek but some consolidation is to be expected.
Sylvania's Q4 update due next Thursday will be a particularly strong one with the rising basket price beginning to take effect from late May and Thaba's Chrome and PGM operations coming online. Last quarter the company raised guidance for the second time in the financial year.
My expectations (note these are estimates) for Q4 2025 to June 30th are:
· Sylvania Dump Operations produced 21,000 4E PGM ounces (Q3 2025: 20,490 4E PGM ounces), heavier rainfall last quarter impacted Lesedi
· SDO produced around 79,000 4E PGM ounces for FY2025 in line with (twice) revised guidance
· SDO recorded $30 million net revenue for the Quarter (Q3 2025: $26.3 million)
· Group EBITDA of $8-10 million (Q3 2025: $6.5 million)
· Cash balance as at 30 June 2025 of $70-75 million (Q3 FY2025 $71.2 million) - slight increase now bulk of capital expenditure for Thaba had been sunk and assuming no further loan advancements to our JV partner Limberg who Sylvania have already lent the best part of $16 million to and which is accruing interest at 11% (repayments begin in 2027)
· Thaba Joint Venture project first chrome production began on schedule in May - we know this to be the case from the 7th May Moneyweb podcast first mine commissioning to crush ore had commenced and they were building up a stockpile ahead of chrome plants. First chrome production was anticipated to begin two weeks later , say, in the next two weeks, and then probably in the two to three weeks after the first PGM production.
· Thaba Joint Venture project first PGM production began on schedule in June - as mentioned in the podcast they were on track to commission in mid June; "two to three weeks after" (chrome production begin).
Outlook
· FY2026 production guidance of 84,000-88,000 4E PGM ounces total (including Thaba JV ) and 200,000t of 'metallurgical grade chromide' revenues to Sylvania (50/50 revenue split)
· Construction of the centralised PGM filtration plant at Lesedi on budget and on schedule for completion around November this year
· Lesedi ramp-up of new ROM plant to steady state production achieved in June - after heavier than normal rainfall during Q3 impacted production
· Dividend / buyback initiatives in FY 2026 due to increase pending review owing to higher basket of metal prices