Eskom asked to integrate additional new-build options into tariff submission
By: Terence Creamer
5th September 2012
"Government was concerned that the MYPD3 application had not catered for likely costs associated with any new Eskom projects beyond the Kusile power station, and had also limited the renewable energy horizon to those associated with the current process to procure 3 725 MW.
O’Flaherty said multiple scenarios had been considered, but Eskom felt it could only submit on the basis of approved projects, or for projects supported by a determination by the Energy Minister Dipuo Peters."
"In other words, the application was not aligned to the Integrated Resource Plan (IRP2010), which implied additional new build costs that could arise during the MYPD3 period.
In fact, Peters indicated recently that she was poised to make determinations that would to transform the Renewable Energy Independent Power Producer Programme into a rolling procurement process in line with the IRP2010. She was also considering new determinations for the procurement of conventional capacity from independent power producers.
However, O’Flaherty said that, in the absence of these determinations or any “direction” on possible future build options, Eskom had had to make a call on what should be included in the application. Eskom also did not agree with the IRP2010’s demand growth assumptions, which had been a major feature in guiding the application."
“[For instance], it is already to late to expect a nuclear programme in 2023 – it’s too late. It’s also too late to expect that there is going to be 500 MW of new coal in 2014, as the IRP2010 indicates, because there have been no decisions.”
http://www.miningweekly.com/article/eskom-asked-to-integrate-additional-new-build-options-into-tariff-submission-2012-09-05