RE: 801 & A6 - Not blocked by rocks ...16 Feb 2023 09:40
Note the 90 meter stuck pipe in the 801 Deep Well to boot hence the sidetrack.
''14/12/2017 7:00am
UK Regulatory (RNS & others)
Caspian Sunrise (LSE:CASP)
RNS Number : 2876Z
Caspian Sunrise plc
14 December 2017
Caspian Sunrise PLC
("Caspian Sunrise" or the "Company")
BNG Operational Update
Introduction
Caspian Sunrise the Central Asian oil and gas company, with a focus on Kazakhstan, is pleased to update the market with news at the BNG Contract Area of progress at its Deep Wells A5, 801, A6 & A8 and at the Shallow Well 146 on the MJF structure.
Deep Wells
Deep Well A5
For 15 days before the formal start of the 90-day flow test the well flowed at the rate of approximately 3,800 bopd using a 10 mm choke. Following a decline in pressure, believed to be caused by drilling fluid in the well, the 10mm choke was replaced with a 4mm choke the production rate fell to approximately 1,000 bopd.
This reduced flow rate is materially less than would otherwise be the case without the drilling fluid in the well. If we continued with the formal 90-day flow test without clearing the well and the choke it would unnecessarily restrict the reserves attributable to the well and the income from sales of oil.
Accordingly, Caspian Sunrise announces a pause to the independent 90-day flow test at Deep Well A5 to allow further drilling fluid to be cleared from the well and from the choke, with a view to materially improving the final result.
We plan to clear the well, possibly with the use of coil tubing equipment, which is on the way to the site. The delay is not expected to be significant and we expect to resume the formal 90-day flow test before the end of the year.
Deep Well 801
As previously announced Deep Well 801 has 90 meters of stuck pipe at a depth of some 4,752 - 4,842 meters.
Work to allow a 200 meter side-track to be drilled from a depth of approximately 4,700 meters is now almost complete and the side-track drilling is expected to commence in the next 10 days, with an expected drilling phase of 30 days.
This is the same operation that allowed Deep Well A5 to flow but at 801 the operation is expected to be easier and quicker as the distances to drill are shorter.''