May have missed it but....29 Mar 2019 07:46
Has there been any update on this?
Over the past nine months the Company has made excellent progress with the construction of the Plant. During November 2018, the technical team completed the front end of the plant comprising the two crusher units, screens, a ball mill and conveyors. This section has been completed and successfully commissioned in December 2018 and has an initial capacity to process 10,000 tonnes per month. The back end of the plant is due to commission in the next week and initial production is scheduled to commence shortly thereafter.