RE: 1 days diference!14 Mar 2022 16:57
Howey,
"SB, if the truth be known, I was just being a little flippant (sorry Nom)." Sorry, that went straight over my head!
Yanis, I agree with your anticipated time line, however we should not be debating this, we should be told..
the vagueness of the communication is not helping the SP and investor confidence.. although i know historically with this angus, specifics haven't always been delivered.. Given the lovely graphic they could produce for the SFB investor update RNS, you think they could manage to produce a Basic Gannt chart and stop us discussing & second guessing the dates because they wont tell us..
I one sense I understand the manage expectations approach but being vague just has me wondering is there something I am missing/ haven't thought about, that posses a risk to completion on time..
For example From the SFB update they stated "Pipe-work is about 15% complete with pipe now being set to racks"
I know as you say below it will be installed and tested between now and commissioning.. I don't see why they could not say the pipework will be complete with installation of last skid (which I assume it will be) or something to that effect.. it would be just reassuring to provide an expected definite end to the pipework installation instead leaving it open ended and open to possible view that potential issue with pipework and have avoided giving end date for reason..
Similar to the "continue to hold "subbies, and "expecting" Q1 gas but might slip into April..in my opinion they new it would be April but provide positive news even if unlikely and cover themselves that the market was informed..