RE: no material changes31 Jul 2020 10:44
As previously announced, the first phase of land required by the Tata Projects and Daewoo Engineering Joint Venture was handed over on 1 April, on schedule, with revenue generated from that date. The Company remains confident of handing over the balance of the 25 acre plot by the end of August.