RE: 202412 Dec 2023 01:49
It's not going to be 2024. I would say optimistically first half of 2025. You can see the history of slippages going back through the annual and half yearly reports. For example:
Annual Report 2021 (released April 22): "Scalable Phase 1 mLNG FID sanctioned 2022 with First Gas expected within 24 months, unlocking the route to cash flow... Phase 2 pipeline gas sales, preparation for FID in 2022 and first revenue in around 24 months, generating significant value thereafter".
Phase 1 notice to proceed occurred in February 2022, so at that stage first gas was being promised in Q4 2023. Phase 2 FID was being promised for 2022, obviously this still hasn't happened and no chance of it this side of 2024.
Half year report 2022 (published early Sep 2022): no dates given in the Phase 1 progress report, but in the chairman's statement Graham refers to : "... Phase 1 which is targeting first LNG delivery by year end 2023 and advancing debt financing for Phase 2, which is planned to fund the majority of the Phase 2 development costs."
Annual report for 2022 (released around May 2023), things are now looking very different: "Project schedule is reviewed constantly and remains challenging. Delivery of a commissioned plant by Italfluid is contracted for Q1 2024."
What? No more first gas in 2023, in fact "full solution commissioning" can't *begin* until at least Q1 2024:
"Consequently, provided that no new disruptive events slow down progress, and the final industrial users are ready to make their process switch from their current fuel to natural gas, LNG plant commissioning and the full solution commissioning including the well and gas gathering system and Afriquia Gaz logistic solution, are both expected to be started in 2024."
Note: no actual mention of a date for first gas/first revenue.
Half year report for 2023 (September 2023): The language is opaque but it now talks about Italfluid "designing and constructing plant equipment for delivery to site in early 2024". Doesn't commit to commissioning in Q1.
"Whilst the mLNG storage tank fabric has been manufactured, there has been some supply chain disruption leading to later than planned delivery to site which remains on the critical path. Despite this, the Company remains committed to commencing production in 2024."
That last statement sounds like hoping against all odds. And if they are relying on hopium for a date that is over a year away, I am willing to bet cash money that they haven't a snowball's chance in hell of meeting it. SOU has never met a deadline under past or present management. We've seen deadlines that, by the due date, are twice as far out as when they started! If Graham says they are committed to 2024, you can only hope that 2025 is still a possibility. Meanwhile there's a lot of money to be found, not to mention a Tendrara exploration well commitment by Sep 2024. Plus they won't have the bondholders' money by 2027. All slippages now have serious consequences.