Or this one from last June which describes how construction should have started in 2010 and got delayed
https://en.radiofarda.com/a/iran-tehran-airport-capacity-delays/29273260.html
"The inauguration of a new terminal at Tehran’s Imam Khomeini Airport (IKIA) that was initially planned to become operational years ago, has been delayed again."
"However, from the beginning, the project has been plagued by systematic delays due to mismanagement. The construction was planned to start early 2010, but a change in plan to make a two-floor terminal instead of the initially planned single-floor, caused a 9-month delay.
The construction finally commenced in 2011, but it was put on hold for several times for further changes in plan and lack of funding. In an effort to attract foreign investment, the Iranian government signed a memorandum of understanding with the French construction company Bouygues in January 2016.
However a year later, Aeroports de Paris, Bouygues’ partner for the Tehran airport terminal development, announced that it would no longer take part in the project, and Bouygues itself decided to withdraw from the deal in May 2017, after it was not able to secure financial backing from international banks, which feared and still fear to be punished by the U.S. government over cooperating with Iran.
Other failures delayed the project furthermore. Among other things, parts of the construction worth of around half a million dollars was demolished last year based on “recommendations” by the Dutch consulting company NACO.
After several rescheduling, the government announced last year that Salam terminal will be launched in June 2018. Yet, when Abbas Akhondi, Iran’s Transportation Minister visited the project on June 2, he only spoke of “summer of this year” as the new inauguration date."