RE: Explore co. Wonβt happen17 Jul 2025 16:37
The TAM drilling isn't progressing that fast though.
15th April RNS said up to 15 holes "expected to commence in early May 2025... The program is expected to take approximately three months with assay results available a month later."
Figure 2 in today's RNS shows only 4 holes complete, after 2 months, with another 3 holes in progress.
Appreciate a 4th rig is being added in the coming week, which will speed things up, but need to get cracking, in particular on pit 2 (where the block model showed highest potential grades).
I accept there is a lead time to get drill pads ready and rigs in place, but feels they are behind where they wanted to be.
Suspect this was a driver for Tranche 2 funds granted recently, to speed this up and fit TAM into overall Cascabel plans. i.e. Franco and Osisko want this moving.