RE: RNS24 Sep 2022 08:54
Good Post @Renewable_Expert, From the figures I can find, with the third turbine up and running the site should be able to produce around 1050MWh per month now (Each turbine seems to be doing around 350MWH per month) increasing to 1400MWH per month with the fourth turbine next year. This should be a stable revenue stream although it's hard to put a figure on it as any useful Financial detail is over a year old.
I would say the next Catalyst would be the approval from Newport Council for the battery site. I can see this coming quite quickly as from the documents on the planning Portal no departments seem to be in objection (Water, Fire Brigade, Highways, Waste, Network Rail)
After that I don't know but possible moves could be :
a) Possible news from Raz Blanchard in Alderney
b) Possible Turbine orders from Japan?
c) Possible Coal Pellets Sale
d) Possible further developments in Newport
e) Repayment of Abundance Interest/ Loans