RE: HH2 & HH-1Z Drilling2 Jun 2019 11:04
No reason at all - in fact the idea seems to have been to drill a sidetrack (-1z) to the current (-1) well, then the new (-2) well, then the -2z sidetrack.
I think they can do limited testing at any time but the big issue maybe that they have to shut-in the current -1 production flow to test the other, new , bores.. = loss on income plus a (small) risk you can't get it restarted when you re-open it .
They're probably optimizing drilling, completion , testing and production schedules all the time . The sequence is easy to change so don't get hung up if they say one thing then do another..
The rig hasn't arrived earlier for several reasons - firstly they didn't contract it before W Newton did and got int front of them, secondly that's going to at W Newton for circa 80- 90 days - seems to be slower drilling than expected & thirdly there seems to be something else that is stopping them signing a rig contract - maybe a partner issue?