Start - Stop5 Oct 2019 20:47
To be expected I'm afraid - we're back to drilling not producing (I know but its the drilling everyone is interested in)
Running casing normally means a clean up wiper trip, a cement job, a wait, drill out, clean up, pressure test - each one is about 8-10 hours
Once they start coring they core 30/60/90 ft and then have to pull the whole sting out 90 ft at a time. They look at the core and decide quit, run another core or drill ahead - still means an other trip to bottom at 90ft per sand. I'd guess 12-15 hours a round trip
So expect a lot of start stop activity into 2020