RE: German Plant22 Dec 2025 13:35
Thanks. We had this in the Q3 results 1st December, just I know Germany pretty much shuts down for Christmas like we do, so I would've thought we may have heard something about the final commissioning and testing by now.
HyProMag Germany
HyProMag Germany is progressing toward establishing a European manufacturing hub for recycled rare earth magnets.
Installation of the HPMS vessel, sieve, blender and jet mill is complete and ready for commissioning. A transverse alignment press is on site, and sintering furnaces are due to arrive in December 2025. Completion and certification of the axial alignment press are in the final stages, with factory acceptance testing scheduled for December 2025. Orders for finishing equipment and expanded sintering capacity will be placed before year-end.
Commissioning of both the HPMS vessel and jet mill is targeted by the end of 2025, with first production expected in Q1 2026, subject to permitting.