RNS - UPDATED RESOURCE ESTIMATE14 Aug 2020 08:08
Updated Resource Estimate - 40% Increase in Indicated Resource, Toral Pb, Zn & Ag Project, Spain
Europa Metals, the European focused lead-zinc and silver developer, is pleased to announce the results of an updated independent Mineral Resource Estimate, reported in accordance with JORC (2012), in respect of its wholly owned Toral lead-zinc-silver project located in northern Spain ("Toral" or the "Toral Project").
Highlights:
· Updated independent Indicated and Inferred Mineral Resource Estimate for Toral, reported in accordance with JORC (2012). The input database for the estimate, included:
o 113 diamond (including wedges) and 4 reverse circulation (RC) drill holes totalling 60,915.65 metres, and 19 underground channels for 18.75 metres.
o Drill holes TOD-024 and TOD-025 and updated fault models for the first time.
· Indicated resource estimate of approximately 3.8Mt @ 8.3% Zn Equivalent (including Pb credits) and 30g/t Ag, representing an approximate:
o 40% increase in Indicated resource tonnes;
o 38% increase in Indicated contained tonnes of zinc to approximately 180,000 tonnes;
o 36% increase in Indicated contained tonnes of lead to approximately 150,000 tonnes; and
o 32% increase in Indicated contained ounces of silver to approximately 3.7 million ounces.
· A total resource of approximately 17Mt @ 6.9% Zn Equivalent (including Pb credits), 4.1% Zn, 2.9% Pb and 24 g/t Ag, including:
o 720,000 tonnes of zinc, 510,000 tonnes of lead and 14 million ounces of silver.
Outlook
The Company expects to utilise the updated resource model, together with ongoing engineering analysis and the upcoming third phase metallurgical results, for assimilation into updated preliminary economic parameters, to be conducted by Bara Consulting, ahead of a Pre-Feasibility Study. The revised economics will represent an update to those derived from the 2018 Scoping Study, bringing the significant amounts of work completed, and data obtained, over the last two years into the operating and financial model for Toral. Prior to establishing the revised economic parameters, the Company intends to announce updates in respect of the third phase metallurgical test work and ore sorting.