RE: Metals Exploration - record year22 May 2026 12:31
Panmure-
2025 was a big year for MTL. Runruno produced record cashflows and the La India gold project in Nicaragua was secured via the acquisition of Condor Gold plc. Development there is being fast-tracked using MTL’s balance sheet and construction remains on track for first gold in Dec 2026 (when Runruno ends). Unaudited production, revenue, earnings and cash flows for 2025 were all released on 28 Jan. BUY maintained, TP unchanged at 30p. Record cash flows in 2025 Production, revenue, earnings and cash flows for 2025 were all released on 28 Jan. US$115m of pre-tax cash flow was a record, despite Runruno production being at the lower end of revised guidance due to contamination issues in the BIOX circuit and the impact of Super typhoon Uwan. Mining will be completed there in H2 2026, and processing by the end of the year, and although 2026 production has been revised lower to 40-48koz due to ongoing toxicity issues and some lost ounces in the new geological model, 2026 cashflows are expected to be similar to 2025. 2026 production of 44koz is -33% vs 2025, PLe for 2026 gold price is US$4366/oz vs 2025’s average of US$3436/oz (+27%). La India – first gold will be a catalyst Construction at La India is tracking ahead of schedule, and is currently c. 50% complete (was 40% in mid-March vs 35% target). Commissioning is expected from Dec 2026 (=key catalyst), with an initial gold pour then too. Commercial production is expected to be declared in Q1 2027 (this is newly confirmed). Bulk earthworks for the plant are complete, as is the ROM pad and first ore has been stockpiled (100kt of 500kt pre-commissioning target as of 23 April). Construction of key infrastructure is ahead of schedule (camp is operational) and MTL’s on site lab should be up and running by the end of Q2 2026. The elution plant is expected on-site in Q3 2026 and is one of the project’s key critical path items … MTL expects a two-month installation period for that. BUY maintained, TP unchanged at 30p.