RE: Kraken shut-in8 Jun 2023 08:36
Our plan is still to restart the Kraken FPSO towards the end of this week, initially on a phased basis, then working up to full production over the coming weeks
I can’t comment on analyst reports following Bumi’s announcement but I can say that we would have already alerted the market of such an issue if we believed there was a reasonable expectation that our production guidance would be materially affected by this shut-in. As things stand, we are losing c.40 Boepd from our annualised production figure for each day that Kraken is fully shut-in. This figure is mitigated in part as we execute planned Q3 maintenance during this period of shut-in
The root cause analysis is ongoing on the transformer failures, with investigations focused on the units themselves and the atmospheric conditions within the electrical room/housing