With the submission of the draft Field Development Plan to the MNR in November 2021, we took an important step towards unlocking the full potential of the Shaikan Field. Constructive discussions continue with the MNR and, while final timing of approval remains uncertain due to the complexity of the project, we are pleased to provide an interim update on the progress that we have made to date on Phase 1 of the draft FDP. Final details and cost estimates may vary and we expect to provide an update upon FDP approval.
As a result of a series of optimisations, we are now targeting to increase Phase 1 gross plateau production to between 85,000-95,000 bopd, including up to 85,000 bopd from the Jurassic reservoir and up to 10,000 bopd from the Triassic reservoir.
In addition, we have updated the Gas Management Plan from processing and export of gas with recovery of elemental sulphur, to reinjection of gas into the reservoir, underpinning our target to eliminate routine flaring and more than halve our scope 1 and 2 emissions per barrel by 2025. The project is expected to be executed in parallel with the Phase 1 increase in oil production.
From FDP approval, the expected duration of the Phase 1 Jurassic and Triassic projects is 36 to 42 months and the Gas Management Plan is 18 to 24 months. Total Phase 1 gross Capex is currently estimated to be $800-$925 million, up around $160 million from the previous FDP with the objective of increasing production towards 95,000 bopd through project optimisations. We continue to review opportunities to further optimise the project.
While the focus remains on delivering Phase 1 of the FDP, we are committed to exploiting the further potential of the field with a vision of increasing production beyond 85,000-95,000 bopd through the expansion of the Triassic reservoir and a Cretaceous reservoir pilot.