winter 21/21 programme28 Dec 2021 10:07
1. Prepack then construct Ice Road and Ice Drillpad to Talitha A then
continue construction to Theta West #1 location 12/15/2021 1/16/2022
2. Move Rig to Talitha A and Rig Up 1/4/2022 1/15/2022
3. Rig Moved to Theta West #1 Coil Unit Moved In at Talitha A 1/15/2022 1/16/2022
4. Theta West #1 well spudded 1/18/2022 1/18/2022
5. Theta West #1 well drilled, cased, tested, and suspended 1/18/2022 4/15/2022
6. Rig downTheta West and move out 4/15/2022 4/30/2022
7. Clean-Up both sites (Winter) 4/28/2022 4/30/2022
8. Clean-Up both site (Summer Stick Picking) – 2 days in Jun or Jul 6/30/2022 7/3/2022