DECREE
Project: SMALL SCALE LNG PLANT – Colle Santo Gas Field
Proponent: LNEnergy S.r.l.
Type: Environmental Compatibility Assessment (ECA)
Article 1 – Environmental Compatibility Assessment
Positive environmental compatibility is granted for the project “SMALL SCALE LNG PLANT – Colle Santo Gas Field” (onshore liquid and gaseous hydrocarbons), including:
A favorable opinion regarding no significant negative impact on Natura 2000 sites, based on a Level II impact assessment.
A favorable opinion on the Preliminary Plan for the use of excavated soil and rocks, as required by Article 24(3) of DPR 120/2017.
These approvals are subject to compliance with environmental conditions set out in Articles 2 and 3.
The decree includes landscape authorization under Article 146 of Legislative Decree 42/2004, as referenced in Article 25(2-quinquies) of Legislative Decree 152/2006, subject to the conditions 1 (1.1–1.4) and 2 in the Ministry of Culture opinion (prot. n. 31042, 18/11/2025).
Validity: The decree is effective for five years from the date of publication on the Ministry of Environment and Energy Security website. After this period, a new environmental impact assessment must be carried out, unless an extension is requested.
Article 2 – Environmental Conditions from PNRR-PNIEC Commission
The proponent must comply with the environmental conditions in the PNRR-PNIEC Commission opinion n. 777 of 24 July 2025.
The proponent must submit a request to start the compliance verification procedures within the terms indicated in that opinion.
Article 3 – Environmental Conditions from Ministry of Culture
The proponent must comply with environmental conditions in the Ministry of Culture note prot. n. 31042 of 18/11/2025.
The proponent must submit a request to start the compliance verification procedures within the terms indicated in that opinion.
Article 4 – Compliance Verification
The Ministry of Environment and Energy Security – General Directorate for Environmental Assessments is the competent authority to verify compliance with the conditions in Articles 2 and 3.
An Environmental Observatory will be established for the project, under the General Directorate for Environmental Assessments, funded by LNEnergy S.r.l., to ensure transparency and monitoring.
The Observatory will include:
Ministry of Environment (Chair)
Ministry of Culture
Abruzzo Region
ARPA Abruzzo (Regional Environmental Protection Agency)
Ministry of Infrastructure – Dams Directorate, for monitoring subsidence, pore pressure, and seismicity, with focus on the Diga di Bomba dam.
Detailed rules for the Observatory will be issued by ministerial decree.
Until the Observatory is fully established, the Ministry will verify compliance using designated offices and personnel, following specific procedures for reporting and timelines.