Thoughts on next news1 Dec 2018 16:34
East Denver:
COGCC shows fraks running on schedule.
On 28th November Frak stages remaining on Thunder and Hagar combined were 39 in total.
If they are still averaging a stage roughly ever 4 hours, then will have completed a further 18 stages by 7pm tonight, and therefore in approx 3 more days would finish those around 7pm Tuesday 4th.
With Citadel the only well remaining (as far as I can work out) there are 47 stages left on that.
That would put us at completing Citadel within 8 days from starting it, on the evening of the 12th. So it’s possible we could get confirmation they are done by the interims.
However, according to the timing of the initial wells it was around 5.7 frak stages a day, if that holds true on these wells also, that would push it out by a few more days... Not sure if the zipper fraking speeds up the two wells being done simultaneously or not, time will tell.
Regardless, after the initial delay on water shortage, it’s really good to see these are still on track with this revised schedule, and as such flowback should start as predicted. Also a bonus to see COGCC doc stating the gas sales line going in also.
Kansas (Rare Gasses)
More guess work than documented evidence here. My hope is that we would have our samples by now, the PSA video
went up on the site two weeks ago on Monday... So pure speculation, but would they have filmed it before it was working, just as it was working, during construction and after? Who knows?! Personally would have thought they’d have it working then look to film it, and if that’s the case it would have been working more than 2 weeks ago...
Either way, with luck and most likely at least two weeks passed since flipping the “on switch”, the samples are hopefully lab bound if not already there? How long to test and next steps from there, unknown, but there is a distinct possibility based on that we could get some news on this before long.
Kansas (Nitrogen)
A certain persons favourite. “Advanced negotiations” but clearly with the PSA etc it’s obvious to see progress has been made on site. I’m guessing at some point we will get an idea on drilling plans or recompletion plans looking at existing plugged wells / data. Clearly the news many crave, we know well drilling / recompletion shouldn’t be expensive per well, and given the flow rate, well payback should be rapid. All about getting the nitrogen off to market I guess, however a further idea on number of wells looking to drill etc could help people realise the size of resource, value of the resource and of course how quickly we can gain revenue from it.
Ephiphany: Expect this is itching to process flowback water en-mass, but won’t be long before it gets it, alongside prod water when Powel and Wildhorse are back online.
Water Resources & DTU: Not going to speculate on further progress with Helios water or DTU. Would expect next news from this will be more information on Epiphany details and how we expand o