RE: Strange24 Feb 2022 12:18
From the company's Jan 27th RNS:-
"Uncertainty remains around the delivery of three final skids on the above table - two of these due to a common sub-component. The Company continues to hold and encourage suppliers and contractors to work to a First Gas date in Q1, but will advise further on this date when able so to do, and does not presently anticipate any delay to shift more than 20-30 days into April."
That's a fact, Gideons... you know, one of those things you do your best to avoid. In the above, its most recent in a series of ever-revised goalpost-moving updates, the company has categorically NOT said it will achieve first gas in Q1 - merely that "it will encourage suppliers to work towards that date" (there's a shocker... what else would it honestly do?).
Those with far more O&G infrastructure commissioning experience have already pointed out from the Twitter pix that even April looks impossible, with maybe May being a best case scenario, provided that there are no more delays on anything at all (equipment required, PP rubberstamping, EA sign-off, NG sign-off etc etc).