RE: Flow rate21 May 2022 13:18
Stockbob, again you seize upon George's massive over-exaggeration and use it in an attempt to deceive.
George claimed on March 10th as follows:-
"The focus is now away from skid delivery to installation with the aim of having the site ready for commissioning during April and producing during May."
(Well, he's clearly already missed that timescale estimate).
"In fact, gross production, of which we have a 51% share, solely from the existing wells and which is wholly unhedged for the month of June, is expected to yield 1.5 million therms or gross revenue of £7.2 million at today's forward price for that month alone."
This was never anywhere near true, even when he said it on March 10th - at that point June gas was priced at around 290p a therm and rapidly falling, and CATEGORICALLY NOT at the 480p per therm that would have been needed to make George's bizarrely inaccurate claim true..
Back to reality (apparently not something that George is used to).. Even presuming he can start production on June 1st (doubtful) and get 1.5 million therms out in the month, yes it all would be unhedged...
...but June gas is priced at 148p per them, so that's £2.22 million of revenue, if he can produce that much and categorically NOT what his Lordship was wildly exaggerating just a couple of months back.
Feel free to fact check any and all info above. It's all freely available and all in the public domain.