RAME23 Feb 2015 22:00
Good evening All,
Just going over some timings -
from the RNS dated 5th Feb, "The transportation of the blades, which are stored at the port of Coronel, is scheduled to commence within 4 days"
and
"Once a blade set has arrived on site, assembly can commence and Rame anticipates that the project construction works will be completed within a period of six weeks, after which final testing of the wind farm as a whole can be concluded."
The first set of 3 off Blades arrived on the 13 Feb.
So, assuming that the 6 weeks (42 days) of construction works start after the first set of Blades arrived and that 10 days have passed since the 13th Feb and we've 5 Turbines to assemble (42/5 = 8.4 days). The first Turbine should be assembled.
If all goes to plan, then all 5 Turbines should be assembled by the 27th March, ish.
Then the testing of the wind farm as a whole can commence.
Anyone know how long this may take?