RE: Stella Rose23 May 2019 16:36
Myo, I sorted it into date order S = Service Shaft, P = Production for anyone that wants to tick them off going forward
S - Winder installation completed Q2-19
S - Head frame, collar and sub collar installation and equipping completed Q3-19
P - Winder installation completed Q3-19
S - Pre-sink to -120 m completed Q4-19
S - Complete assembly and installation SBR Q4-19
P - Head frame, collar and sub collar installation and equipping completed Q1-20
P - Pre-sink to -120 m completed Q2-20
P - Complete assembly and installation SBR Q2-20
S - First Polyhalite Milestone Q4-21
S - Sink to shaft bottom -1,538 m Q1-22
P - Sink to shaft bottom -1,622 m Q3-22
S - Shaft equipping, change-over and commissioning Q1-23
P - Shaft equipping, change-over and commissioning Q2-23