RE: Getting close1 Feb 2020 10:20
Good morning psyche8
You wrote ; "Does anyone think we could get FID as soon as we get UKEF approval, whilst sanction would be some time off"
I copied and paste these definitions of Sanction and FID;
" Project Sanction means the final approval by the Proponents to fund the engineering, procurement and construction of the subsea template and associated subsea facilities to be installed in connection with the development of the Unit as described in the Development Plan."
"In the energy project context, FID stands for “Final Investment Decision”. ... It's when the project execution phase begins and the big money starts being spent on project construction (i.e. often when an EPC contractor gets to work).3 Mar 2016"
We are some way from FID according to NAVITAS own published documents I re-post a section I put up here previously.
I translated from Hebrew a PDF form Navitas dated 7th January;
"2.1.3 Signature Deadline - The Parties will act to sign the Transaction Agreements by February 28, 2020, or Until a later date to be agreed by the parties."
Only once that's signed off will the FIG be sent the proposed new partnership terms.
The FIG have to approve the new arrangements. What will they make of them?
Our RNS of the same date gives us an estimation of how long FIG approval may take;
"Finalisation of a Sale and Purchase Agreement is expected during Q1 2020 ("SPA Signing") with completion subject to satisfaction of certain conditions including regulatory approval, expected in Q2 2020 ("Farm-in Completion")"
So its April to end of June before we may get FIG approval.
Its only at that point, I think its fair to say, would NAVITAS start to fund raise.
The Navitas document has these useful comments;
"? Final Investment Decision (FID) for 1 Phase Development - in accordance with information provided to Partnership by Existing partners, such a final investment decision is expected to be made by the end of 2020.
This is after the financing outline for the development of this phase has been completed."
"? Production start - according to information provided to the partnership by existing partners, start of production
The oil asset is expected during 2024."