2023 plan as published26 Jul 2023 09:52
2023 Exploration and Development Workplan:
Gold Projects
Nalunaq
In preparation for the 2023 field season and enabled by the debt financing, Amaroq is finalizing mine design and schedule for the up-dip portion of the Mountain Block, thus laying the groundwork for a trial mining area. In order to realise this the Nalunaq project team is working on:
Site Preparation - June to August, the site will undergo logistical planning, detailed engineering design, procurement and mobilization of equipment and project teams in preparation for underground development as well as construction of associated infrastructure.
Mine Preparation - August to January, following the mobilization of equipment and personnel, the existing developments in the Mountain Block will be re-opened and rehabilitated with all required mining services installed.
Trial Mine Operation - January 2024 onwards, Amaroq intends to commence a new operation within the Mountain Block with trial mining and ore production feeding an initial stage (gravity circuit) trial processing facility constructed on the valley floor.
In addition to this and to facilitate progressive resource growth in this trial mining area, the Company is conducting a programme of mountain drilling in the trial mining area and further up-dip
Nanoq
The 2022 season saw the completion of a 407.65 km2 high-resolution heli-borne geophysical survey across the Nanoq, Siku and Jokum's Shear gold projects with the aim of defining geological models to direct future drilling campaigns.
These results have highlight a number of additional targets which will be assessed during field investigations in 2023 as well as site preparation ahead of initial drilling in 2024.
Vagar Ridge
While Amaroq will focus its efforts on the development of the Nalunaq deposit during 2023, Amaroq will aim to construct a robust geological and mineralisation model to inform future exploration at Vagar. Ground preparation and drill readiness preparations will also occur ahead of the 2024 season.
Strategic Minerals Projects (Amaroq 51%)
Sava
The 2022 field season saw the completion of a two drillhole scout drilling programme across two target areas along with associated mapping and sampling across the licence.
Amaroq has proposed a 2023 season incorporating further scout drilling on at least two separate IOCG targets along with further ground exploration in the form of geological and alteration mapping guided by external IOCG specialists.
North Sava
An airborne geophysical survey of approximately 5,100 line-km was completed across the North Sava sub area targeting the continuation of the mineralisation and mineral potential already identified at interpreted by the Amaroq geology team and external consultants with conclusions are exannounced in H2-23.
Kobberminebugt Licence
Samples of the main Josva vein returned up to 11.6 % Cu over 0.5 m. Minor gold and silver grades were also reported.
The 2023 fieldwork plan