RE: 17-2-2023. Portfolio Update: Thacker Pass Lithium Royalty19 Feb 2023 07:20
Am sure they would like to bring it forward but given all the permitting hurdles they have already gone through I think it would be very difficult to commence Phase 2 any earlier than planned.
Originally, in 2018, Phase 1 and 2 was for 30,000 tonnes each with an anticipated production date of Q4/2022 and Q3/2026 respectively.
Subsequently the targeted tonnage levels were increased in 2021 following larger resource estimates (by lowering the cut-off grade) and the increased tonnage for Phase 2 would take longer to achieve due permitting plus increased capacity arising from efficiency gains.
Compared to the initial timescales things obviously took longer than anticipated and now we have first production slated for Phase 1 and 2 being H2/2026 and H1/2030 with each phase contributing a boiler plate 40,000 tonnes.
The production profile is Year 1, 20k tonnes, Years 2 & 3, 38,000k and not getting to full capacity of ~70k tonnes until year 5, meaning it will not be until 2035 before Trident starts to see the real money coming in (although as the recent TRR presentation stressed it is the NAV that drives the share price).
The above timescales/production depends on the claimed recovery efficiencies being realised and construction is completed on time. Neither of which are far from certain. Then there is also the question of how lithium price and how that may change over the next 12 years.