Dubhe well timelines.5 Jun 2025 05:18
I gleaned this from co pilot :-) seems like public comments is now officially closed which imo means no objections were raised as per below notice.
The Alaska Department of Natural Resources issued a public notice regarding the Dubhe-1 exploration well by Great Bear Pantheon, LLC. Here are the key details:
* Project Overview: The company submitted a Unit Plan of Operations Application on March 19, 2025, seeking approval to construct a gravel pad and drill the Dubhe-1 exploration well.
* Location: The proposed gravel pad will be 1,500 feet west of the Dalton Highway, about 27 miles south of Deadhorse, within the Talitha Unit (TAU).
* Construction Details: The gravel pad will measure 500 feet by 310 feet, covering 3.56 acres. A gravel drivewaywill be five feet thick, 50 feet wide, and 1,400 feet long.
* Support Facilities: The site will include a satellite office camp, storage areas for fuel and drilling waste, and maintenance buildings.
* Timeline: Gravel work is expected to begin on May 15, 2025, followed by drilling operations in July 2025.
* Public Comments: The Division of Oil and Gas is accepting written comments until May 6, 2025, at 4:30 pm Alaska Time. Comments can be sent via email to dog.permitting@alaska.gov or mailed to their Anchorage office.