RE: Question?17 Oct 2025 10:46
Going back to 10 June RNS, we're hoping that preparation for step 1 is now nearing completion...
"1. Finalising Plant Design: Engineering design studies for the Pinon Canyon Plant are advancing with flow data and gas analysis from the recently completed drilling campaign being integrated. The final design of the helium and CO2 processing plant will be determined once all of the gas analysis and flow modelling has been completed.
2. Site Development: Civil works will commence at the approved Pinon Canyon Plant location once the final plant layout is determined.
3. Equipment Mobilisation: Following site preparations, mobilisation of the plant equipment to the Pinon Canyon site will be undertaken.
4. Well Tie-Ins and Compression: Tie-in of initial production wells, including any necessary well-site gas compression, will proceed alongside plant site civil works.
5. Commissioning: Upon completion of the Pinon Canyon Plant and individual well tie-ins, the plant will be tested and commissioned. This is subject to standard operational permits, environmental compliance, and final readiness assessments."