RE: 88 RNS out28 Feb 2022 23:07
Think this is how it works out….IMO
7th March 2022-14th March 2022
The well is planned to be initially drilled to 2,000 feet, with the surface casing then installed and the Blow Out Preventer system tested. .
14th March 2022-11th April 2022
Drilling to TD is then *expected to take a further four weeks, including wireline logging.
11th April 2022-18th April 2022
Flow testing of Merlin-2 will be contingent upon the wireline results, in particular the MDT outcomes, as well as government approvals and weather window considerations.
A production test program for the Merlin-2 well has been designed and equipment placed on standby during initial well site operations.