RE: Only the beginning10 Jan 2022 23:53
M_Night,
So, if we don't need 20,000m, how much do we need?
George doesn't know himself because he needs to get verified assay results which will inform the DFS modelling to get to the 60-80mt target. By taking this approach any schedule acceleration from saving a few thousand metres of drilling are offset by having to wait for the verified lab results and the modelling of the resource to be completed to ensure it is in the right ball park.
So, at this point in time, if PREM are targeting getting Zulu to 60-80mt there is no way the can set out how much drilling is required to get that. Which in turn means there is no control of the programme.
This is the difference between a GR interview which is full of potential, conjecture and jam tomorrow and the obscure carp he provides in his RNSs.
Bickmaster