RE: Rig19 Jul 2018 14:35
Sorry that time includes transportation and setting up. This from recent RNS
On arrival at Pointe-Noire, and after all relevant customs checks and documentation have been completed, the rig will be transported the 40km by road from the port to the drill site at Tilapia. Once onsite and rigged-up, a full pre-drill inspection of the rig will take place by both an international rig inspection company contracted by AAOG and drilling contractor SMP Drilling. Depending on the time taken to clear customs, this stage could take between three and four weeks.